2.10 DIMENSIONS

2.10.1

Overall Width:

 

36”

48”

 

 

Discharge chute down

46.25” (117.5 cm)

58.25” (148.0 cm)

 

 

Discharge chute up (Transport only)

36.1” (91.7 cm)

48.1” (122.2 cm)

2.10.2

 

Overall Length:

 

48”

 

 

36”

 

 

 

 

 

77.0” (196 cm)

73.0” (185 cm)

 

2.10.3

 

Curb Weight:

 

 

48”

 

 

 

36”

 

 

 

 

 

517 lbs. (234 kg)

565 lbs. (256 kg)

 

Weights will vary slightly depending on engine option.

2.10.4Overall Height:

2.10.5Tread Width (to outside of tires):

 

36”

48”

 

44.1” (112 cm)

44.1” (112 cm)

 

36”

 

 

48”

 

35.2” (89.4 cm)

35.2” (89.4 cm)

2.11 TORQUE REQUIREMENTS

BOLT LOCATION

TORQUE

Blade Mounting Bolt

55-60 ft-lbs. (75-81 N-m)

Cutter Housing Spindle Nut

140-145 ft-lbs. (190-197 N-m)

Mower Deck Support/Engine Deck Mount

30-35 ft-lbs. (40-47 N-m)

Engine Mounting Bolts (15 HP Kawasaki)

15-20 ft-lbs. (20-27 N-m)

Transmission Shifter-lever Nut

30-35 ft-lbs. (40-47 N-m)

Anti-Scalp Roller Bolts

40-45 ft-lbs. (54-61 N-m)

Wheel Lug Nuts

90-95 ft-lbs. (122-129 N-m)

3.ASSEMBLY INSTRUCTIONS

3.1Uncrate unit, and remove upper handle assembly, fuel tank, and linkages from top of crate.

3.2Remove and open the bolt bag.

3.3Loosen the 5/16" hardware at the two (2) discharge deflector hinge points so that the deflector is snug, but can be moved up and down freely.

3.4Refer to Parts Manual to help you identify and locate parts and their proper position.

3.5Apply retaining adhesive “Fel-Pro Retaining I or Retaining II” or “Loctite RC609 or 680” on the two threaded studs from the bolt bag and install into the two left holes underneath fuel tank. Install the fuel tank on top of the fuel tank support with the studs going through the slots in the support. Install two 5/16-18 x 3/4” screws with a 5/16” SAE flat washer and 5/16” lock washer into the threaded holes in the right side of the fuel tank. Do not over tighten. Place a 5/16” SAE flat washer, then a spring, over each of the studs and fasten with a 5/16 nyloc nut. Tighten 5/16 nyloc nut fully then back off a 1/2 turn. This is to allow for normal fuel tank expansion with changes in temperature and fuel levels.

3.6Attach the fuel tank hose to the tank fitting and secure with the clamp provided.

3.7Position the lower end of the handle assembly on the outside of the upper rear section of the fuel tank and handle support. Install four 3/8-16 x 1" bolts (with four spring disk washers against the head of each bolt) from the outside in. Secure using four 3/8" whizlock nuts on the inside of each handle support and tighten until the spring disk washers are flat (See Figure 1).

-10 -

Image 15
Contents For Serial Nos 540,000 & Higher Potential Hazard Exmark Parts PLUS→ Program Operators Manual Maintenance & Adjustments Table of Contents SafetySpecifications Assembly InstructionsTraining SafetySafety Alert Symbol Your Safety is InvolvedCarbon monoxide can kill you Operation Potential Hazard Page Maintenance and Storage Safety SignsRiding Attachments Page Page Specifications Assembly Instructions DimensionsTorque Requirements Upper Handle Mounting Speed Control Throttle Cable HOOK-UPPTO Engagement Linkage This Clearance should be Equal Shifter Lever To Transmission Drive Lever Linkage Installation Drive Lever Setting Controls Operation InstructionsNeutral LOCK/PARK Brake Latch PRE-STARTOperating Instructions Drive LEVER, Neutral LOCK/PARK Brake Latch Operation Transporting Periodic Maintenance Maintenance & AdjustmentsBlade Bolt Installation Must stop Page Spray Lubricant Chart Grease Lubrication ChartPage Cutting Height Adjustment AdjustmentsPTO Engagement Linkage Page Waste Disposal Trouble ShootingEngine Troubleshooting Engine Troubleshooting TableProblem Wiring Diagram 15 HP Kawasaki Year Limited Warranty Page Service Record Fold Along Appropriate Line See EXMARK’S Complete Line of Accessories