| '_ LISTED VENT CAP |
| 2 FT. MINIMUM ABOVE ANY OBJECT |
3 FT. MINIMUM | WITHIN 10 FT. HORIZONTALLY |
Piping Installation
SUPPORT |
|
|
| Piping, fittings, | and | valves should be installed according | ||||||
|
|
|
| to the installation drawing (Figure 13). If the indoor |
| |||||||
*MAINTAIN |
| TYPE | B DOUBLE | installation | area is subject to freezing | temperatures, | the | |||||
CLEARANCE |
| |||||||||||
| WALL | VENT PIPE | water piping must be protected | by insulation. |
| |||||||
|
|
| ||||||||||
t |
|
|
| The water supply pressure should not exceed 80 psi. If | ||||||||
| **MAINTAIN | this occurs, | a pressure | reducing | valve | with | a bypass | may | ||||
|
| |||||||||||
|
| _ SPECIFIED | need to be | installed | in the cold | water | inlet | line. This | should | |||
VENT |
| CLEARANCE | be placed on the supply | to the entire | house in order | to | ||||||
|
|
| ||||||||||
CONNECTOR |
|
| maintain equal | hot and | cold water pressures. |
| ||||||
SLOPE UP |
|
|
| |||||||||
1/4 IN. PER | FT. |
|
| IMPORTANT: | Heat | cannot be applied | to the water fittings | |||||
MINIMUM |
|
|
| |||||||||
1 |
|
|
| on the heater as they may contain nonmetallic parts. If | ||||||||
|
|
| solder connections | are used, solder the pipe to the adapter | ||||||||
VERTICAL GAS VENT SYSTEM WITH |
| before attaching the adapter to the hot and cold water | ||||||||||
| fittings. |
|
|
|
|
|
|
|
| |||
TYPE B DOUBLE | WALL | VENT PIPE. |
|
|
|
|
|
|
|
|
| |
FIGURE | 11. |
| IMPORTANT: Always use a good grade of joint compound | |||||||||
| and be certain | that | all fittings are drawn up tight. |
|
|
|
|
|
| 1. | Install the water |
| piping and fittings as shown | in Figure | |||
|
|
| LISTED | VENT CAP |
| 13. Connect the cold water supply (3/4" NPT) to the | ||||||
|
| 5 FT. MINIMUM |
|
|
| cold water inlet fitting. Connect the hot water supply | ||||||
|
|
|
|
| (3/4" NPT) | to the | hot water outlet fitting. |
|
| |||
|
| f |
| MAINTAIN |
|
|
| |||||
|
|
| SPECIFIED | IMPORTANT: | Some | models may contain | energy saving | |||||
|
|
|
| CLEARANCE | ||||||||
SUPPORT |
|
| heat traps to prevent the circulation of hot water within the | |||||||||
|
| pipes. Do not remove the inserts within the heat traps. | ||||||||||
STRAP. |
|
|
| |||||||||
*MA,NTA,N\ |
|
| 2. | The installation | of unions in both the hot and cold water | |||||||
CLEARANCE | __SEAL |
|
| |||||||||
|
|
| supply lines is recommended for ease of removing the | |||||||||
| ] | _ll |
|
|
| |||||||
|
|
|
| water heater for service or replacement. |
|
| ||||||
|
|
|
|
|
|
|
| |||||
|
|
|
|
| 3. The manufacturer of this water heater recommends | |||||||
VENT |
|
| CONNECTOR |
| installing a tempering valve or an | device | ||||||
|
|
|
|
| in the domestic | hot water line as shown in Figure | 14. | |||||
CONNECTOR |
| UNUSED CHIMNEY |
| |||||||||
|
|
|
| These valves reduce the | temperature | of | ||||||
1/4 IN. PER | FT. |
| OR MASONRY |
| ||||||||
MINIMUM |
|
| ENCLOSURE |
| the water | by mixing cold and hot water | and | are readily | ||||
|
|
|
|
| ||||||||
|
|
|
|
|
| available for use. |
|
|
| |||
|
|
|
|
| 4. | If installing | the water heater in a closed water system, | |||||
|
| VENTING THROUGH | A CHIMNEY WITH |
|
| install an expansion tank in the cold water line as |
| |||||
|
| TYPE B DOUBLE WALL VENT PIPE. |
|
| specified under Closed System/Thermal Expansion. | |||||||
|
|
|
|
|
| |||||||
|
| FIGURE | 12. |
| 5. | Install a |
| valve in the cold water inlet | line. It | |||
* Maintain vent pipe clearance requirements to local, state |
| should be located close to the water heater and be | ||||||||||
| easily accessible. Know the location of this valve and | |||||||||||
and/or the "National Fuel Gas Code", ANSI Z223.1 (NFPA |
| |||||||||||
| how to shut off the water to the heater. |
|
|
| ||||||||
edition. |
|
|
|
|
|
| ||||||
|
|
|
|
|
|
|
|
|
|
** NFPA 211, Standard for Chimneys, Fireplaces, Vents, and | 6. A temperature and pressure relief valve must be | |
installed in the opening marked "Temperature and | ||
Solid | ||
Pressure (T & P) Relief Valve" on the water heater. | ||
intended to be installed in accordance with the installation | ||
A discharge line must be added to the opening of | ||
instructions provided with each chimney support assembly. | ||
the T&P Relief Valve. Follow the instructions under | ||
Minimum air space clearance to combustible materials should be | ||
Temperature and Pressure Relief Valve. | ||
maintained as marked on the chimney sections. | ||
7. After piping has been properly connected to the water | ||
| ||
| heater, remove the aerator at the nearest hot water | |
| faucet. Open the hot water faucet and allow the tank | |
| to completely fill with water. To purge the lines of | |
| any excess air, keep the hot water faucet open for | |
| 3 minutes after a constant flow of water is obtained. | |
| Close the faucet and check all connections for leaks. |