ADCP-61-471 • Issue 4 • June 2000 • Section 2: Operation and Maintenance

NTP-004

Page 1 of 2

SYSTEM OR CIRCUIT PROVISIONING PROCEDURES

Summary: This procedure tells how to provision (turn-up) a new Soneplex system or circuit using the Craft Interface. The procedure assumes the equipment in the Soneplex chassis and the equipment at the other end of the circuit has been installed, and has passed all local and end-to- end tests. Some procedures may not be required and will depend upon how the system is equipped. This procedure must be performed before attempting to operate the entire circuit or system that will be using this equipment.

Do Items Below

For Details Go To

1.

Log on to the Craft Interface.

DLP-526

2.

Clear Alarm History (required only for a new installation).

DLP-527

3.

Set system date and time, and enter the Target Identifier.

DLP-528

4.

Set Craft Interface port configuration:

 

 

• For Craft Port on MPU or Port 2

DLP-549

 

• For X.25 Port

DLP-558

5.

Edit Menu Security (set privilege levels).

DLP-536

6.

Edit User Accounts (set user IDs and passwords).

DLP-535

7.

Assign names to Housekeeping Alarm contacts.

DLP-550

8.

Configure the DS3 MUX as required, set service state, and set

 

 

protect status. If required, insert Line Build-Out on the transmit

 

 

side of the DS3 signal.

DLP-529

9.

If present, equip ODS2 modules; assign service state and line code

 

 

for each DS1 on the ODS2 module.

DLP-530

10.

If present, equip Version C, D, E, or G HLXC modules and

 

 

provision HDSL circuits.

DLP-516

11.

If present, equip DLX modules and provision DS1 circuits.

DLP-532

12a.

If present, equip RLX modules and provision DS1 circuits.

DLP-534

 

AND/OR

 

12b.

If present, equip RLXIOR modules and provision DS1 circuits.

DLP-533

13.

Assign performance monitoring thresholds for each DS1 in the

 

 

system.

DLP-556

2-14

© 2000, ADC Telecommunications, Inc.