Do Items Below in The Order Listed

For Details Go To

4.Momentarily press the LMPTST switch on the APU front panel and verify that all indicators light.

5.

Connect terminal equipment to Craft port on the front of the MPU.

DLP-504

6.

Log on to the Craft Interface.

DLP-526

7.

Clear Alarm History.

DLP-527

8.

Enter Target Identifier and set date and time now or during

 

 

provisioning (the turn-up process).

DLP-528

9.

Configure DS3 MUX as required.

DLP-529

10.

Configure HLXC modules as required.

DLP-531

11.

Check the HLXC to HLXR voltage and current:

 

 

• Version C HLXC to HLXR Voltage and Current Test.

DLP-568

 

• Version D (or Later) HLXC to HLXR Voltage and Current Test.

DLP-572

12.

Connect the test equipment at both ends of the system and perform an

 

 

end-to-end test between the chassis and the remote HLXR.

DLP-520

13. If the DS3 MUX protect module is installed:

• Execute Force/APS commands through the Craft Interface.

DLP-537

Perform Manual (Force) Switch to Protect test on DS3 MUX

module.

DLP-511

• Perform APS test on DS3 MUX module.

DLP-512

14.Coordinate the test with a technician located at the remote end of the circuit and ensure test procedures there have been completed. Refer to the Soneplex Version D HLXR Remote System Operation and Maintenance Manual, listed under Related Publications at the beginning of this manual.

15.At both ends of the circuit, make any necessary cross-connects at

 

the distribution frames.

DLP-515

16.

Log off from the Craft Interface system.

DLP-564

17.

Complete assignment forms and update office records as required by

 

 

local procedures.