Using Accessory Lift Kit

Using Accessory Lift Kit

 

Lifting Bracket

Spreaders

Accessory

(Field Supplied)

Sheet Metal

 

 

Screw

 

To avoid possible

 

damage to unit

 

panels from lifting

 

clevis, place

 

packing material

 

between clevis

 

and panels before

 

lifting unit.

Figure 1

Units may also be moved or lifted with a forklift while still in the factory-supplied packaging. The lengths of the forks of the forklift must be a minimum of 42".

Roof Curb Installation

Roof Curb Assembly

Figure 2

If a roof curb is used, follow the manufacturer’s Installation Instructions and be sure that all required clearances are observed (see following Clearances section).

Clearances

All units require certain clearances for proper operation and service. Refer to Table 1 for the minimum clearances to combustibles as well as minimum clearances necessary for servicing and proper unit operation.

Minimum Clearance Requirements

 

To

For

For

 

Combustible

Proper

 

Service

 

Material

Operation

 

 

 

 

 

 

Front

0"

48"

3"

 

 

 

 

Rear

0"

24"

3"

 

 

 

 

Condenser

0"

24"

3"

End

 

 

 

 

 

 

 

Blower

0"

30"

0"

End

 

 

 

 

 

 

 

Top

0"

36"

36"

 

 

 

 

Table 1

Service Access

Access to all serviceable components is provided by four removable panels: filter compartment, blower compartment, heater compartment, and top panel.

Condensate Drain

The PHP package unit is equipped with a 3/4" FPT coupling for condensate line connection. Plumbing must conform to local codes. Use a sealing compound on male pipe threads.

The condensate drain line must be properly trapped and routed to a suitable drain. See Figure 3 for proper drain arrangement. The drain line must pitch to an open drain or pump to prevent clogging of the line. Seal around the drain connection with suitable material to prevent air leakage into the return air system.

Typical Condensate Drain Connection

Unit

Drain Connection

1.00" Min.

In the U.S., units may be installed on combustible floors made from wood or classA, B, or C roof covering material. In Canada,

12.00"

Max.

3.00" Min.

units may be installed on combustible floors.

Positive Liquid Seal Required

Figure 3

506248-01

Issue 0902

Page 3 of 14