3.Multiple Dryer (common) Venting

If it is not feasible to provide separate exhaust ducts for each dryer, ducts from individual dryers may be channeled into a "common main duct." The individual ducts should enter the bottom or side of the main duct at an angle not more than 45º in the direction of airflow and should be spaced at least 46-inches (116.84 cm) apart. The main duct should be tapered, with the diameter increasing before each individual duct (16- inch [40.64 cm] minimum) is added.

IMPORTANT: The ML-96 is not provided with a back draft damper unless the damper option was purchased. When exhausted into a multiple (common) exhaust line, a back draft damper must be installed at each dryer duct.

IMPORTANT: No more than three (3) dryers should be connected to main common duct.

The main duct may be any shape so long as the minimum cross section is provided. The illustration on page 19 shows the minimum cross section area for multiple dryer round or square venting. These figures must be increased 10 square inches (64.5 square centimeters) when rectangular main ducting is used, and the ratio of duct width to depth should not be greater than 3-1/2 to 1. These figures must be increased in proportion if the main duct run from the last dryer to where it exhausts to the outdoors is unusually long (over 20 feet [6.1 meters]) or has numerous (more than two [2] elbows in it). In calculating ductwork size, the cross section area of a square or rectangular duct must be increased twenty percent (20%) for each additional 20 feet (6.1 meters). The diameter of a round exhaust must be increased ten percent (10%) for each additional 20 feet (6.1 meters). Each 90º elbow is equivalent to an additional 36 feet (10.97 meters) and each 45º elbow is equivalent to an additional 15 feet (4.57 meters).

IMPORTANT: For extended ductwork runs, the cross section area of the ductwork can only be increased to an extent. Maximum proportional ductwork runs cannot exceed 15 feet (4.57 meters) with two (2) elbows. When the ductwork approaches the maximum limits as noted in this manual, a professional heating, venting, and air conditioning (HVAC) firm should be consulted for proper venting information.

IMPORTANT: Exhaust back pressure measured by a manometer at each dryer exhaust duct area

must not exceed 0.3 inches (0.75 mb) of water column (W.C.).

The ductwork should be smooth inside with no projections from sheet metal screws or other obstructions, which will collect lint. When adding ducts, the duct to be added should overlap the duct to which it is to be connected. ALL ductwork joints must be taped to prevent moisture and lint from escaping into the building. Inspection doors should be installed at strategic points in the exhaust ductwork for periodic inspection and cleaning of lint from the ductwork.

NOTE: When the exhaust ductwork passes through a wall, ceiling, or roof made of combustible materials, the opening must be 2-inches (5.08 cm) larger than the duct (ALL the way around). The duct must be centered within this opening.

18

Page 22
Image 22
American Dryer Corp ML-96D installation manual