VANITY INSTALLATION

Provide suitable reinforcement required for anchoring the vanity to the wall. Centerline of reinforcement should be 32- 3/4" up from the floor (see Figure 1).

The molding needs to be notched to seat the vanity flush against the wall (see Figure 2).

Rough in supply lines and waste per rough in dimensions.

NOTE: If current supply lines are greater than 6" on center, they may interfere with cutout in rear of vanity or vanity shelf.

Remove the wood top from the vanity. The top is held in place from the underside by 4 screws, 1 through each of the 4 angled corner braces.

Move the vanity into place and anchor it to the wall through at least 2 of the anchoring holes in the rear of the vanity (see Figure 2).

Continue with installation appropriate for top and sink options chosen.

C/L of 2 x 6

Reinforcement

32-3/4"

FIGURE 1

Finished

Floor

 

21-1/4"

 

540mm

 

ANCHORING

 

HOLES

FIGURE 2

32-3/4"

 

 

832mm

 

MOLDING

Wood Top with Recommended Sinks...

Two people recommended for this installation

PAPER TEMPLATE

Determine which sink is being installed and follow the instructions printed on the appropriate template supplied with vanity.

NOTE: American Standard is not responsible for cut-out errors when the incorrect cut-out template is used.

If Installing:

Use Template:

WOOD VANITY TOP

 

 

 

 

 

 

 

 

 

 

Sebring 0573

730541-400

IMPORTANT: BE SURE TO CENTER SINK

Coventry 0575

730542-400

CUT OUT HORIZONTALLY ON VANITY TOP.

 

 

After top is replaced, connect the trap to the drain assembly hand tight to check alignment. It may be necessary to cut off part of the tailpiece (area "A") or part horizontal leg of the trap (area "B").

Connect hot and cold supply lines to the shut off valves. Tighten trap joints for watertight assembly.

B

A

- 2 -

730548 - 100 Rev . B

Page 2
Image 2
American Standard 9532.200 installation instructions Vanity Installation, Wood Top with Recommended Sinks