Installing Equipment
WARNING
TIP HAZARD
This cabinet is easily tipped. Follow the precautions below during and after equipment installation.
•Make sure you have secured the cabinet to the floor before installing equipment.
•Install the heaviest equipment first toward the bottom of the cabinet to prevent the cabinet from becoming
•Do not extend equipment on sliding rails until you have installed 158 kg (350 lbs) of equipment into the bottom of the cabinet for stability or until you have installed the
Failure to follow these instructions can result in death, serious injury, or equipment damage.
To install
1.Review the equipment manufacturer’s installation instructions.
2.Locate the top and bottom
3.Install the cage nuts on the interior of the vertical mounting rail; then install the equipment. (To remove a cage nut, squeeze the sides to release it from the square hole.)
Vertical Mounting Flange Cutouts
NetShelter SV 800 mm (31.5 in.) wide cabinets have removable vertical mounting flange cutouts along the sides. When removed, side airflow is increased. Other airflow and cable management options exist. Please visit the website (www.apc.com) for other options and more information.