Installation | |
|
|
Installation
Unpacking and Handling
YOU are responsible for filling all freight claims with the delivering truck line. Inspect all cartons and crates for damage as soon as they arrive. If damage to cartons or crates is found, or if a shortage is found, note this on the bill of lading (all copies) prior to signing.
If damage is found when the equipment is opened, immediately call the delivering truck line and follow up the call with a written report indicating concealed damage to your shipment. Ask for an immediate inspection of your concealed damage item. Packaging material MUST be retained to show the inspector from the truck line.
Do not place heavy objects on top of the unit or damage could occur. The units are not structurally designed to support excessive external loading.
Move the unit as close as possible to its permanent location before moving it off of the shipping pallet. Make certain there are no separately packed accessories before discarding packaging.
Floor Model
Follow the procedure below to level the unit and mount the kick plates. See Figure 2.
1.Slide kick plates, ends first, between the base frame and outer panels. Secure in raised position with tape. Make sure that the end kick plates fit behind the front and rear kick plates.
2.Using a carpenter’s level on the lowest shelf, level the unit by adjusting the leg levelers at the corners of the unit.
3.Raise the low end of the unit to level it, do not lower the high end.
4.Check for level
5.Remove the tape holding the kick plates in raised position.
6.Make certain that the kick plates are flush to the floor.
7.Drill 9/64” diameter holes in the base frame to match the
8.Attach the kick plates to the base frame with the #8x1/2” black sheet metal screws provided (SCR355).
9.Seal kick plates to floor using a
6