Fig. 2 — Installing Fittings and Valves, 30HX (Typical)
30GXN,R UNITS ONLY — Using good brazing practice, braze the
Step 3 — Dehydrate and Recharge Circuit —
When piping has been completed, leak test the assembly. If one of the
After leak testing, evacuate, dehydrate, and recharge the cir- cuit using an approved refrigerant recovery device. Correct type and amount of refrigerant are listed on unit nameplate and in base unit documentation.
Step 4 — Install Control Wiring
Be sure all power to the unit is off before proceeding. Lock out and
Wires between
codes and NEC (National Electrical Code, U.S.A.). Wire size must be no. 16 AWG (American Wire Gage) (1.5 mm2) mini- mum. See Fig. 4 and 5 for field wiring.
30HX UNITS — Remove the screws holding the
Route wires through
30GXN,R UNITS
ALL UNITS — Using good wiring practice, connect a white wire from the solenoid valve on circuit A to a white wire from the solenoid valve on circuit B. Connect both wires to
Connect a pink wire to the solenoid valve on circuit A.
Connect a gray wire to the solenoid valve on circuit B. Con- nect both the pink and gray wires to
Figure 4 shows the correct location of the wiring connection points on the chiller.
3