Installation 11

Installation

Step 1: Mounting

1Layout the concrete pad as detailed in Figure 4. Be sure to locate electrical conduit inside the hatched 14" x 13" area.

2Excavate required area for pad and conduit. Pad depth should be below the frost line, or as required by local codes.

3Locate four 1/2" X 6" long L-bolts (not supplied) as shown in Figure 4. The L-bolts should protrude 1 1/2" inches above the pad.

4Pour concrete, insuring that the pad is level and above the ground line.

5 Allow the concrete to set at least two days before installing gate.

Figure 4: Concrete Pad Layout