28
|Installation
AC Mains
Wall
2-pole
Breaker
UPS
Line
Neutral
Figure 19. Circuit Breaker Diagram
To hardwire the UPS input:
1Switch off utility power at the distribution point where the UPS will be connected. Be absolutely
sure there is no power.
2Remove the terminal block cover (four screws) and retain.
Figure 20. Removing the Terminal Block Cover
3Punch a hole in the terminal block cover for the input conduit using a Greenlee® punch or similar
device. The hole accommodates 3/4 or 1 IMC conduit.
4Pull the input wire through the conduit, leaving approximately 2 ft (0.5m) of exposed wire. Attach
a flexible metal fitting to the end of the conduit.