VENTILATION

VENTILATION

!WARNING

Never use heater without properly installed vent pipe and regulator. You must vent heater to the outdoors. This assures proper combustion and avoids air contamination in the room.

A standard 4 inch (10.16 cm) draft regulator is required only if total vertical and horizontal length of the vent pipe exceeds 20 feet (6.1 meters). Regulator, vent pipe, and fittings are not supplied with the heater. Purchase these items at a local hardware store.

Standard 4 inch (10.16 cm) draft regulator (required if vent pipe ex- ceeds 20 feet [6.1 meters] in length).

30" (76.2 cm) Mini- OPERATION mum

If horizontal run is needed, use at least 1 foot (30.48 cm) rise for each 10 feet (3.05 meters) of run.

OPERATION

125 VENTILATION

PFA/PV 023

Figure 4 - Ventilation Requirements

!WARNING

Review and understand the warnings in the Safety Informa- tion Section. They are needed to safely operate this heater. Follow all local codes when using this heater.

To Start Heater

1.Follow all ventilation and safety information.

2.Fill fuel tank with kerosene or No.1 fuel oil.

3.Attach fuel cap.

4.Plug power cord into standard 230 volt/50 hertz, grounded (earthed) outlet. Use an extension cord if needed. Use only a three-wire, grounded (earthed) extension cord.

Extension Cord Wire Size Requirements

Up to 100 feet (30.5 meters) long, use 16 AWG (1.0 mm2 ) conductor

101 to 200 feet (30.6 to 61 meters) long, use 14 AWG (1.5 mm2 ) conductor

Heater will start when power cord is plugged into outlet. If not, push in flame- out control reset button (see Figure 5).

Flame-Out

Control

Reset Button

(Fan Guard

Removed)

Figure 5 - Flame-Out Control Reset Button