INSTALLATION (continued)

INSTALLATION (continued)

Figure 1-4. Maintenance handle operation and contact position indicators.

observe these lights

Figure 1–5. Standard controls and indicators.

2 – Voltage Checks

First check nameplate on transfer switch; rated voltage must be the same as normal and emergency line voltages.

Use extreme caution when using a meter to measure voltages in the following steps.

Do not touch power terminals; shock, burns, or death could result !

Perform steps 1 through 6 at the right. Observe the status lights. See Figure 1–5.

O Black circle means light is on.

P White circle means light is off.

* If necessary, adjust voltage regulator on the

generator according to the manufacturer’s recommen-

dations. The Automatic Transfer Switch will respond

only to the rated voltage specified on the Transfer

 

Close the normal source circuit

 

 

breaker. The Normal Transfer

Source Accepted

1

Switch Position and the Normal

Normal

 

Source Accepted lights should

 

Emergency

 

come on.

 

 

 

Use an accurate voltmeter to

 

 

check phase to phase and

 

2 phase to neutral voltages pres-

 

 

ent at the transfer switch normal

 

 

source terminals.

 

 

Close the emergency source

Source Accepted

 

circuit breaker. (Start generator,

3

if necessary.) The Emergency

Normal

 

Source Accepted light should

Emergency

 

come on.

 

Use an accurate voltmeter to check phase to phase and

4 phase to neutral voltages pres- ent at the transfer switch emer- gency source terminals.*

Switch nameplate.

Use a phase rotation meter to

A B C

5 check phase rotation of emer- gency source; it must be the same as the normal source.

Shut down the engine–genera-

 

tor, if applicable. The Emergen-

Source Accepted

cy Source Accepted light should

6 go off. Then put the starting

Normal

control selector switch (on the

Emergency

generator set) in the automatic

 

position. Close enclosure door.

 

Now continue to 3 – Electrical Operation on next page.