Emerson 300 manual 3 – Electrical Operation, INSTALLATION continued, Transfer Test

Models: 300

1 20
Download 20 pages 36.92 Kb
Page 9
Image 9
3 – Electrical Operation

INSTALLATION (continued)

observe these lights

press this button

Figure 1–6. Standard controls and indicators.

3 – Electrical Operation

This procedure will check the electrical operation of the Automatic Transfer Switch. See Figure 1–6.

Close the transfer switch enclosure door and tighten the screws before you test electrical operation.

Transfer Test

Both normal and emergency sources must be available and the emergency source generator (if used) must be capable of being started in this procedure.

Perform steps 1 through 8 at the right. Observe the status lights. See Figure 1–6.

OBlack circle means light is on. P White circle means light is off.

NOTE: If Motor Load Transfer feature is activated, then transfer may not occur immediately after the respective time delays. Transfer will only occur when the phase relationship between sources is correct.

This completes the Functional Test of the ASCO Series 300 Automatic Transfer Switch. Leave the engine–generator starting control in the automatic position.

 

The normal source must be

 

 

available and the generator

Source Accepted

1 must be ready to start.

Normal

 

Check that the Normal Source

 

Emergency

 

Accepted light is on.

 

 

 

Press and hold the Transfer Test

 

2

button until the engine starts

Transfer

and runs. This should happen

Test

 

within 15 sec.

 

3

The Emergency Source

Source Accepted

 

 

Accepted light should come on.

Normal

 

 

Emergency

 

The transfer switch should

 

 

transfer to the Emergency

Transfer Switch

4

position. The Emergency

Position

Transfer Switch Position light

Normal

 

should come on and the Normal

Emergency

 

light should go off.

 

 

If the transfer to emergency

 

 

delay is used the transfer

 

5

should occurs after a time delay

Bypass

(up to 5 minutes).

Time Delay

 

For immediate transfer press

 

 

the Bypass Time Delay button.

 

 

The transfer switch should

 

 

transfer back to the Normal

Transfer Switch

6

position. The Normal Transfer

Position

Switch Position light should

Normal

 

come on and the Emergency

Emergency

 

light should go off.

 

 

If the retransfer to normal delay

 

 

is used the retransfer should

 

7

occur after a time delay

Bypass

(up to 30 minutes).

Time Delay

 

For immediate retransfer press

 

 

the Bypass Time Delay button.

 

 

The unloaded running delay

 

 

keeps the generator running for

Source Accepted

8

5 minutes (cool–down period).

Normal

Then the generator should stop

 

and the Emergency Source

Emergency

 

 

 

Accepted light should go off.

 

1---5

Page 9
Image 9
Emerson 300 manual 3 – Electrical Operation, INSTALLATION continued, Transfer Test