PREPARE HOT WATER LINE

Installation Preparation

PREPARE HOT WATER LINE

The line may enter from either side, rear or floor within the shaded area shown in Figure F.

The line may pass through the same hole as the electrical cable and drain hose. Or, cut an additional 1-1/2" diameter hole to accommodate the water line. If power cord with plug is used, water line must not pass through power cord hole.

 

1-1/2" Dia.

4"

5" 4"

 

5"

 

Shut-off Hole

 

 

Hot

Valve

 

 

 

 

 

 

2"

 

6"

 

 

 

 

From

19" From Wall

 

Cabinet

 

Cabinet FaceWater Line Connection

Figure F

2" From Floor

Water Line Connection

Turn off the water supply.

Install a hand shut-off valve in an accessible location, such as under the sink. (Optional, but strongly recommended and may be required by local codes.)

Water connection is on the left side of the dishwasher. Install the hot water inlet line, using no less than 3/8" copper tubing. Route the line as shown in Figure F and extend forward at least 19" from rear wall.

Adjust water heater for 120°F to 150°F temperature.

Flush water line to clean out debris.

The hot water supply line pressure must be 20-120 PSI.