Installation Manual For Indoor Unit
a b c d e f g h i
1002 483.5 131 1105 255 105 880 970 220

a

b

c

d

e
f

g

h

i

Fig 2
After selecting the unit installation location, proceed the following steps:
Installation dimension: (Unit: mm)
1. Drill a hole in the wall and insert the connecting pipe and wire through a PVC
wall-through tube purchased locally. The wall hole shall be with a outward down
slope of at least 1/100. (See Figure 2)
2. Before drilling check that there is no pipe or reinforcing bar just behind the drilling
position.
Drilling shall avoid at positions with electric wire or pipe.
3. Mount the unit on a strong and horizontal building roof. If the base
is not firm, it will cause noise, vibration or leakage.
4. Support the unit firmly.
5. Change the form of the connection pipe, connection wire and drain
pipe so that they can go through the wall hole easily.