Assembling the sliding rack kit

Assembling the sliding rack kit

To assemble the sliding racks:

GB

A

1.Remove the two frames, lifting them away from the spacers A (see figure).

Left

Right guide

guide rail

rail

 

B

 

 

 

C

 

 

of

 

 

Direction

 

 

extraction

2.Choose which shelf to use with the sliding rack. Paying attention to the direction in which the sliding rack is to be extracted, position joint B and then joint C on the frame.

D

3.Secure the two frames with the guide rails using the holes provided on the oven walls (see diagram). The holes for the left frame are situated at the top, while the holes for the right frame are at the bottom.

4. Finally, fit the frames on the spacers A.

￿Do not place the sliding racks in position 5.