Telescopic Stack Installation

Telescopic Stack Installation

6.Align the telescopic stack to the pre-drill holes on the ceiling and securely fasten to the joists and cross framing lumber with eight screws (not provided). Make sure screws are driven into center of joists and cross framing lumber for maximum support.

7.Adjust the blower unit to the telescopic stack using reference F calculated in TABLE 1 on page 4 and measurements on pages 14-15. Tighten blower unit to the telescopic stack with four (M5 x 15) screws (provided) as shown in Figure 4.

Wiring to Power Supply

Wiring to Power SupplySAFETY WARNING

RISK OF ELECTRICAL SHOCK. THIS RANGE HOOD MUST BE PROPERLY GROUNDED. MAKE SURE THIS IS DONE

BY QUALIFIED ELECTRICIAN IN ACCORDANCE WITH ALL APPLICABLE NATIONAL AND LOCAL ELECTRICAL CODES. BEFORE CONNECTING WIRES, SWITCH POWER OFF AT SERVICE PANEL AND LOCK SERVICE PANEL TO PREVENT POWER FROM BEING SWITCHED ON ACCIDENTALLY.

8.Route house wiring into the ceiling as close to the installation location as possible. Allow additional length to drop down from the ceiling to the electric box.

9.Connect the electrical wires according to color (green to green, white to white, and green to green) and cap with wire connectors as shown in Figure 5. Green wire must be grounded to reduce risk of electric shock.

Figure 4

Figure 5

Figure 6

Ductwork Installation

10.Use 7” round aluminum or steel pipe (not provided) to connect the 7” round damper on the hood to the ductwork above. NOTE: Place 7” round duct pipe over the damper. Seal with duct tape to make all joints secure and air tight. NOTE: MAKE SURE FLAPS ON DAMPER CAN OPEN & CLOSE FREELY. (Figure 6)

6

Page 8
Image 8
Kobe Range Hoods IS2442GSB Telescopic Stack Installation, Wiring to Power Supply, Ductwork Installation, Safety Warning