INSTALLATION

INSTALLATION

RECEIVING & UNPACKING EQUIPMENT

1.Check packing slip to ensure ALL material has been delivered.

2.All material shortages are to be reported to Walter Meier (NORTEC) within 48 hours from receipt of goods. Walter Meier (NORTEC) assumes no responsibility for any material shortages beyond this period.

3.Inspect shipping boxes for damage and note on shipping waybill accordingly.

4.After unpacking, inspect equipment for damage and if damage is found, notify the shipper promptly.

5.All NORTEC products are shipped on an F.O.B. factory basis. Any and all damage, breakage or loss claims are to be made directly to the shipping company.

6.Each distributor is provided with: installation manual, one hose cuff, and two hose clamps.

PRE-INSTALLATION CHECK

1.Ensure the total capacity of the humidifier is not higher than the allowable maximum steam capacity of the distributors used.

ASD 10: 22 lbs/hr (8 kg/hr)

ASD: 25 lbs/hr (9 kg/hr)

BSD: 35 lbs/hr (13 kg/hr)

CSD: 115 lbs/hr (45 kg/hr)

STEAM LINE INSTALLATION

GUIDELINES

1.Nortec steam hose should only be used on short steam runs below 10 feet.

2.Ensure that no condensate produced in the steam line will remain trapped. Steam naturally flows upward and condensate naturally flows downward.

3.See material recommended for use in the chart below. To eliminate the metal corrosion, Nortec does not recommend the use of steel piping.

Chart #1

Steam Line Material

 

Steam
Copper Tube
Stainless

 

Hose

 

Steel Tube

 

 

 

 

Short run

￿

￿

￿

< 10 feet

 

 

 

(3 m)

 

 

 

 

 

 

 

Long run

 

￿

￿

> 10 feet

 

 

 

(3m)

 

 

 

 

 

 

 

DI / RO

 

 

￿

water

 

 

 

 

 

 

 

 

 

 

 

4.Consult the following pages for step by step distributor installation starting with Figure #1.

5.Consult the charts below for steam and condensate sizing guidelines when using steam distributors.

Chart #2
Recommended material and size for steam run

Load

Steam Run

Steam

 

 

 

 

 

Steam Line

 

 

 

 

Line

 

 

 

 

Description

 

 

 

 

 

 

 

 

Material

lb/hr

kg/hr

ft

m

 

 

 

 

 

 

 

 

 

0-30

0-13

0-10

0-3

Copper

3/4" MED-L Tubing

tube

(7/8" O.D.)

 

 

 

 

0-30

0-13

10 +

3 +

Copper

1” MED-L Tubing

tube

(1 1/8" O.D.)

 

 

 

 

0-30

0-13

0-10

0-3

Stainless

7/8” tube x

Steel tube

0.049” thick.

 

 

 

 

0-30

0-13

10 +

3 +

Stainless

1 1/8” tube x 0.049”

Steel tube

thick.

 

 

 

 

30-100

13-45

0-20

0-6

Copper

1 ½” MED-L Tubing

tube

(1 5/8" O.D.)

 

 

 

 

 

 

 

 

 

 

30-100

13-45

20 +

6 +

Copper

2” MED-L Tubing

tube

(2 1/8" O.D.)

 

 

 

 

30-100

13-45

0-20

0-6

Stainless

1 ¾” tube x

Steel tube

0.065” thick.

 

 

 

 

30-100

13-45

20 +

6 +

Stainless

2” tube x

Steel tube

0.065” thick.

 

 

 

 

Please note that options shown in a bold-italic font requires that reducers be used at both ends. These extra large sizes are to allow for better condensation removal in long steam runs. These sizes will not permit you to use hose coupling to connect your self to either humidifier or distributors.