Electrical Work

The electrical work should be performed by a specialist qualified for the work.

Use the single phase power supply, and be sure to install the sub power distributing board for exclusive use with the unit (separately purchased by the user).

Avoid multiple connecting wiring as it can cause a drop in voltage, thus resulting in poor performance of the automatic control circuit.

Be sure to install circuit breaker (separately purchased by the user).Be sure to connect the grounding wire.

The indoor unit is powered by the outdoor unit by means of a H07 RN-F connection cable (or a more power model), with insulation in synthetic rubber and jacket in polychloroprene(neoprene), in accordance with the requirements of standard IEC 60335-2-40.

1.Remove the screw on the electrical component box and remove the cover plate.

2.Route the connection cord through the side of the indoor unit and connect the cable to terminals.

3.Route the other end of the cable to the outdoor unit through the ceiling & the hole on the wall.

4.Reassemble the electrical component box cover, carefully tightening the screw.

Wiring Standard

ITEMSPEC

 

 

 

Power

Single phase 220V~, 60Hz

 

 

 

Circuit Breaker

Earth Leakage Circuit Breaker(ELCB) 30A

 

 

 

Electric wireBelow 20m2.5mm2
Below 50m4mm2

 

 

 

 

Allowable voltage

198V~242V

 

 

Min. size of electric wires from/to the indoor/

0.75mm2

outdoor units

 

 

 

 

You must compress the solderless ring to the cable and then connect it to the main power terminal.

Solderless ring selection

Thickness of cable(mm2)

B(mm)

d2(mm)

Silver solder

2.5

Less than 9.5

More than 4.5

 

4

Less than 9.5

More than 4.5

 

36_ installation part