![](/images/new-backgrounds/1266418/26641813x1.webp)
VCAUTION
CONDUCTING DIELECTRIC AND/OR
Do not perform dielectric or high potential
tests with the TPS3 unit installed.
V DANGER
Hazardous voltage.
Will cause death or serious injury.
Keep Out.
Qualified personnel only.
Disconnect and lock off all power before working on this equipment.
TPS3 11 Installation Instructions
Common Problems to Avoid
•Confirm System voltage to SPD voltage (120V SPD will fail instantly on 240V, 277V, etc.)
•Locate SPD close so leads are short & straight as possible (or will seriously hurt performance)
•Make sure
•Energize SPD AFTER system is stabilized & checked (inadvertent system problem may fail SPD)
•SPDs are regulated by NEC®Article 285 and UL 1449
•Never
Figure 4: Conduit Installation
CORRECT INSTALLATION
Threaded 6 Full Turns
INCORRECT INSTALLATIONS
• | Meet all National and Local codes (NEC® Article 285 addresses |
| SPDs) |
• Mount SPD as close to panel or equipment as possible to keep leads | |
| short |
• | Ensure leads are as short and straight as possible, including neutral |
| and ground. Consider a breaker position that is closest to the SPD and |
| the panel’s neutral & ground |
• Suggested breaker & conductor size is | |
• Make sure system is grounded per NEC® and clear of faults before | |
| energizing SPD. |
1. | Use a voltmeter to check all voltages to ensure correct SPD |
2. | If unit has Flush Mount option refer to Flush Mount Installation |
| Instructions following |
3. | If SPD has Dry Contact |
4. | Remove power for panel. Confirm panel is deenergized. |
5. | Identify breaker location and SPD location |
6. | Remove an appropriately sized knockout from panel |
7. | Mount SPD, use appropriate weatherproofing equipment as |
POOR ENGAGEMENT Conduit needs to be threaded in farther
Figure 5: Typical Panel Installation
To Protected Loads
OVERTIGHTENED
Stresses box, ONLY 6 full turns required
| needed |
8. | Connect conductors as appropriate – short and straight as possible |
| (Note that |
9. | Label or mark conductors as appropriate (neutral: white, ground: |
| green, energized: black, |
10. Make sure system is bonded per NEC® and is clear of hazards or | |
| faults before energizing |
| #1 cause of SPD failures) |
11. | Energize and confirm proper operation of indicators and/or |
| options |
A sealing
Note that any conduits must be installed correctly.
A B C
BREAKER
N
•Use closest breaker to SPD
•Locate SPD close to intended breaker
•Keep Leads Short as Possible • Avoid Sharp Bends
G
|
| E |
|
|
|
|
|
|
|
| |
|
| SERVIC | 1 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| |||
|
|
|
| - |
|
|
|
|
| • | Rotate TPS3 11 such |
|
|
|
| TYPE 1 SURGE |
|
|
|
| |||
|
| CAUTION |
| ||||||||
|
|
|
|
|
|
|
|
| that LED indicator is | ||
|
| RDANGEV |
| WWW.SIEMENS.COM | PROTECTIVEDEVICE |
|
|
|
|
| |
|
|
|
|
|
|
|
| ||||
|
|
|
|
|
|
|
| most visible | |||
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
•Outdoor installation requires appropriate weather sealing at nipple
etc.)
7