PAGE 5
19A SERIES BOILER
INSTALLATION INSTRUCTIONS
TABLE 3
STEP 1 | UPPER RIGHT | 5 FT. LBS. |
STEP 2 | LOWER LEFT | 5 FT. LBS. |
STEP 3 | UPPER LEFT | 5 FT. LBS. |
STEP 4 | LOWER RIGHT | 5 FT. LBS. |
STEP 5 | UPPER RIGHT | 25 FT. LBS. |
STEP 6 | LOWER LEFT | 25 FT. LBS. |
STEP 7 | UPPER RIGHT | 50 FT. LBS. |
STEP 8 | LOWER LEFT | 50 FT. LBS. |
STEP 9 | UPPER LEFT | 10 FT. LBS. |
STEP 10 | LOWER RIGHT | 10 FT. LBS. |
|
|
|
Prepare additional intermediate sections and install in the same manner described above. Be sure each section is properly sealed against water leakage and flue gas exfiltration. Be certain the angle rails remain level and provide support for each section as it is assembled. Check each section for vertical position.
When all sections, including the front section or back are in place, check all draw rods to insure
HYDRONIC
SEAL
CORRECT
HYDRONIC
SEAL
INCORRECT
SEALING
FIGURE 3
7.HYDROSTATIC TEST
Plug tappings, fill boiler with water and vent air from top of boiler. Check for leaks. Leakage at seals may be due to misalignment of hydronic seals. Loosen draw rods, reposition seals and retest as above.
All completed boilers shall satisfactorily pass the hydrostatic tests as prescribed by A.S.M.E., Code Section IV.
1.Steam Boilers – The assembled boiler shall be subjected to a hydrostatic test of not less than 45 PSIG.
2.Water Boilers – The assembled boiler shall be subjected to a hydrostatic test pressure not less than
3.The required test shall not exceed the test pressure by more than 10 PSI.
Excessive torque on draw rods may damage castings. Do not exceed the torque shown in TABLE 3.
In a cold environment, hydronic seals may not quickly conform to sealing surfaces when properly compressed. Under such conditions, hydrostatic testing with cold water might show weeping or leaking at the seals. To avoid this possibility, delay filling the boiler with cold water for a few hours after assembly, or use warm water, if available, for the tests.
If there is seepage about chaplets or minor leakage, consult the Smith Company representative for advice regarding A.S.M.E. Code approved repairs by peening or plugging.
8.STEAM PIPING
A steam piping schedule is shown in TABLE 4. Pitch piping to allow condensate to flow in the same direction as steam. Makeup water connections must be made to the return piping, not directly to the boiler. Install
See FIGURE 4 for recommended acceptable steam piping arrangement.
TABLE 4
BOILER SIZE | NO. OF 3" RISERS | HEADER | EQUALIZER |
3 THRU 5 SECTION | 1 | 3" | |
6 THRU 10 SECTION | 2 | 4" | 2" |
11 AND 12 SECTION | 2 | 5" |
STEAM SUPPLY
TO SYSTEM | GATE VALVE | |
| ||
3" STEAM RISER(S) | ||
SUPPORT DISCHARGE |
| |
PIPE | STEAM HEADER | |
EQUALIZER | ||
* | ||
CONNECTION | ||
| ||
TERMINATE DISCHARGE | BOILER WATER LINE | |
PIPE SO AS TO AVOID | 41 1/4" ABOVE FLOOR | |
DISCHARGE ON PERSONS |
| |
GATE VALVE |
| |
ALTERNATE RETURN |
| |
CONNECTION | 2" BELOW MINIMUM | |
C.W. MAKEUP | ||
BOILER WATER LINE | ||
CONNECTION | ||
| ||
GATE VALVE | * SAFETY VALVE | |
| ||
RETURN | BLOWDOWN VALVE | |
CONNECTION | TO DRAIN | |
|
TYPICAL STEAM PIPING DIAGRAM
FIGURE 4