Check-Out Procedure
Check off steps as completed:
❏1. Boiler and heat distribution units filled with water?
❏2. Automatic air vent, if used, opened one full turn?
❏3. Air purged from system? Piping checked for leaks (including tankless heater, if used)?
❏4. Air purged from oil piping? Piping checked for leaks?
❏5. Flue cap in place and tightened? Burner door closed, sealed and nut tight? Burner plugged in and service switch on?
Obtain
leakage and carbon monoxide emissions, leading to severe personal injury or death.
❏6. Proper draft and burner flame? Final adjustment made with combustion test equipment?
❏7. Test limit control: While burner is operating, move indicator on limit control below actual boiler water temperature. Burner should go off while circulator continues to operate.
Raise setting on limit control above water temperature and burner should
❏8. Test additional
❏9. Limit control set to system temperature requirements (max. 220°F)?
❏10. For multiple zones, flow adjusted to distribute heat in all zones?
❏11. Thermostat heat anticipator setting
(if available) set properly? Refer to “Connect wiring,” page 18.
❏12. Boiler cycled with thermostat? Raise to highest setting and verify boiler goes through normal
❏13. Observed several operating cycles for proper operation?
❏14. Set room thermostat(s) to desired
room temperature?
❏15. Completed Installation and Service Certificate below?
❏16. Reviewed Maintenance and Service Manual with owner or maintenance person and instructed person to keep for future reference?
❏17. Returned all instructions provided with boiler to its envelope and placed with boiler for future reference?
Installation and Service Certificate
Date Installed: ______________________________________________ | ❏ Installation instructions have been followed. |
Boiler Model Number: __________________Series: _________ | ❏ |
CP Number(s):______________________________________________ | ❏ Above information is certified to be correct. |
Measured Btu or GPH Input: _____________________________ | ❏ Information received and left with owner/ |
|
| maintenance person. | |
Installer:__________________________________________________________________________________________________________________________ | |||
| (Company) | (Address) | (Phone) |
|
|
| |
22 |
| _________________________________________________________________ | |
|
|
| (Installer’s Signature) |
|
|
|