Attach Top Link to Backhoe

1. Attach top link (1) to the main frame using two

1. 1017875

Top link

cap screws (7), four hardened flat washers (16),

2.

37670

Double top link

and two hex nuts (8).

7.

14334

3/4 NC x 3 HHCS GR5

 

2. Slide double top link (2) over top link (1) and

8.

1450

3/4 NC Hex nut

secure using two cap screws (10) and lock huts

10.

34157

7/8 NC x 3-1/2 HHCS GR5

(12). See Figure 3.

12.

34194

7/8 NC Lock nut

 

NOTE: To estimate the overall length of the two

16.

57798

3/4 Hardened flat washer

top link bars; roughly measure from the center of

 

 

 

the tractor top link bracket to the center of the

 

 

 

lower 3-point lift arm pivot as shown in Figure 3.

 

 

 

Final adjustment will be made when backhoe is

 

 

 

attached to tractor.

 

 

 

Figure 3. Top Link Installation