Step 7: Performing Checks Prior to Initial Start-Up
Before testing your installation, ensure these conditions are met:
pChassis and AC grounds are properly installed.
pAC input connections and AC output connections are wired correctly on the
terminal block and not reversed.
pPositive (+) battery cable is connected to the positive (+) battery terminal
through the DC fuse and disconnect switch or DC circuit breaker.
pNegative (–) battery cable is connected to the negative (–) battery terminal.
pBattery voltage is within the proper range for this unit
(10.3–15.3 volts DC).
pDC disconnect switch or breaker is turned off.
pAC input and output breakers are turned off.
pAll connections are tight.