Generac 20kW owner manual Maintenance Level

Page 22

Standby Generator Sets

Service Schedule

Maintenance

Level 1

 

Level 2

 

Level 3

 

Level 4

 

Tasks

Recom-

Task

Required

Task

Required

Task

 

Task

 

mended

Comp.

to be done

Comp.

to be done

Comp.

Required

Comp.

 

to be done

(Date-

3 months/

(Date-

Semi-

(Date-

to be done

(Date-

 

monthly

Initials)

Break-in

Initials)

annually

Initials)

Annually

Initials)

13.Initiate an automatic start and transfer of the unit to

site load and exercise it for at least 1 hour looking for leaks, loose connections or components, and abnormal operating conditions. Correct as necessary.

14.Start and exercise the unit at full rated load (use a

load bank if the site load is not enough) for at least 2 hours looking for leaks, loose connections or components, and abnormal operating conditions. Correct as necessary.

15. Change the engine oil.

16.Replace the engine oil filter(s).

17.Replace the engine air filter(s).

18.Replace the engine fuel filter(s) on diesel engine driven units and re-prime the fuel system.

19.Check the engine spark plugs on gas engine driven units. Clean and re-gap or replace as necessary.

20.Perform a 5 minute no-load operational run of the unit looking for any post service problems.

21.Return the unit to standby

setup for operation when required.

11-3

09/05 A .Rev SrvSchd002

Image 22
Contents Centurion Standby Generator Sets Table of Contents  Warning   Electrical Hazards  Authorized Service Dealer Location ‹ Operation and Maintenance‹ HOW to Obtain Service IntroductionGenerator SET Data Generac Power SYSTEMS, INCIdentification Record ‹ Data LabelEngine OIL Recommendations Equipment DescriptionCoolant Recommendations Engine Protective Devices ‹ Natural GAS Fuel System Fuel System‹ Fuel Requirements ‹ LP Fuel SystemSpecifications ‹ Reconfiguring the Fuel System ‹ Cold Weather KIT‹ 3-PHASE Alternators Alternator Power Winding Connections‹ FOUR-LEAD, SINGLE-PHASE Stator Generator AC Lead ConnectionsPreparation Before START-UP InstallationInitial Inspection for QT Genset Startup ‹ Preparation for START-UP START-UP Checklist‹ START-UP Inspection ‹ Engine START-UP and Transfer Operating Unit with Manual Transfer SwitchGenerator Control Operation ‹ Retransfer and ShutdownCooling System Checking Fluid LevelsMaintenance Owner Operator can Perform ‹ Changing Engine OIL ‹ Changing the Engine AIR Cleaner ‹ Coolant Change‹ Spark Plugs Miscellaneous Maintenance Service Schedule Service Maintenance Interval InformationLevel Maintenance Level Troubleshooting Guide Problem Cause CorrectionStandby Generator Sets Standby Generator Sets Page Breaker Tray BACK/BOTTOM Page Assy Rotor 20KW Page Battery Tray C1 CPL Page Mounting Base 1.5L C1 CPL Page Support Radiator LH Side Page ASM Motor Stepper Page ENGINE-1.5L Page Elbow 90D 3/4 NPT Page Roof C1 CPL Page Muffler C1 Page Page Page Page Page Page Standby Generator Sets Warranty