Honda Power Equipment L14-20R installation instructions Installation Instructions

Page 3

INSTALLATION INSTRUCTIONS

1.Determine where you want your EmerGen Switch located, either to the left or right of the load center. The switch should be approximately 18” from the center of the load center, making sure that there is plenty of room to properly connect the flex conduit whip.

2.TURN OFF POWER. The main circuit breaker in your load center should be switched to the OFF position. CAUTION—this does not affect the wires on the line side of the main breaker—they will remain live! Remove the cover of the load center.

3.Identify 3/4'' knockout to remove.

4.Insert the wires from the flex conduit up through the knockout; take care not to nick or gouge the wires on the metal edge. Tighten the locknut securely onto the load center. The wires can hang freely.

5.Without over-manipulating the flex conduit, secure your EmerGen Switch to the wall with fasteners appropriate for the wall’s construction. If you are mounting this unit flush to the wall, follow instructions included with the Flush Cover Kit.

3

Image 3
Contents Manual Transfer Switch Safety Information Installation Instructions Wiring the EmerGen Switch to the Load Center Installing 240 Volt 2 pole Circuits Completing the Installation EmerGen SwitchLoad Management Operation / Test ProcedureTrouble Shooting