Generac 6382 manual Installation Procedure, Model

Page 2

NOTE ON NEUTRAL BONDED GENERATORS: Some portable generators are intended for use on jobsites and are subject to OSHA regulations for GFCI protection on all receptacles. These "contractor grade" generators have their neutral wire bonded to the ground wire to pass OSHA inspection. When connected to a transfer switch, this may cause nuisance tripping of the generator GFCI breaker. When using a neutral bonded generator to power a house or building through a transfer switch, consult the generator manufacturer or local authorized service dealer to determine if the neutral bond wire on the generator can be disabled without voiding the warranty. If it can be disabled, then no modifications to your transfer switch installation are needed. If the neutral bond cannot be removed or voids the warranty, you must install a Switched Neutral Kit (SNK, Generac model 6297) accessory with your transfer switch. NOTE: Removal of the neutral bond should be performed by an authorized generator service dealer or qualified electrician. If the neutral bond is removed, the generator will no longer pass OSHA inspection for job sites.

TABLE 1 - SPECIFICATIONS

MODEL:

6382

6335

UTILITY MAIN breaker, Included

200 Amp

200 Amp

GEN MAIN breaker, included

30 Amp

50 Amp

Max Load per Circuit

As marked

As marked

Max Load on Generator

30 Amp

50 Amp

Max Watts @ 250 Volt

7500

12,500

Max Watts @ 125 Volt

7500

12,500

Max 1-pole Circuits *

12

12

Max 2-pole Circuits *

6

6

NEMA Configuration of Power Inlet

L14-30

CS6365

Voltage

125/250 Volts

125/250 Volts

NEMA Type Enclosure

3R – Outdoor

3R – Outdoor

Phase

1

1

Minimum Gauge Cord Size

10/4 AWG

6/4 AWG

*NOTE: If Ground Fault Circuit Interrupting (GFCI) breakers, Arc-Fault breaker or surge protecting circuit breakers are used in the transfer switch, they will reduce the maximum number of circuits from the number shown in the table above. Also if circuit breakers larger than 50 amps are used as sub-feed breakers, the maximum number of circuit breakers will also be reduced. Contact your local installer or dealer for more information on GFCI, Arc-Fault and Surge Protecting circuit breakers. Because GFCI and

AFCI circuit breakers can take up more than one space, the overall maximum number of circuits may be reduced from the number shown.

STEP 1: INSTALLATION PROCEDURE:

HAZARDOUS VOLTAGES ARE PRESENT INSIDE TRANSFER SWITCH ENCLOSURES THAT CAN CAUSE DEATH OR SEVERE PERSONAL INJURY. FOLLOW PROPER INSTALLATION, OPERATION AND MAINTENANCE PROCEDURES TO AVOID HAZARDOUS VOLTAGES. TURN OFF THE MAIN CIRCUIT BREAKER IN THE LOAD CENTER BEFORE STARTING INSTALLATION.

1.Although this transfer switch can be installed above, below or on either side of the utility meter socket, the preferred location is to the RIGHT of the meter socket since the location of the lugs for the Utility Main are on

the Left side of the transfer switch. Knockouts (KO) are provided only in the bottom of the enclosure. However, since the enclosure is aluminum, it is easy to cut in the desired knockout. If the KO is cut in above the live terminals of the circuit breakers, a watertight hub should be used. NOTE: If a 2” KO is cut in the side of the Transfer switch enclosure, the dead front panel may need to be “notched” to clear the 2” fittings. The back of the KO must be 3/8” from the rear of the enclosure.

2.Loosen the thumb screw from the cover of the transfer switch, and slide the cover down to remove. The thumb screw stays attached to the cover.

3.Remove the two screws from the bottom of the dead front. When the cover is pulled forward, the snap-in closing plates will fall out. Set the front cover and dead front aside for reinstallation after wiring.

4.The mounting holes in the back of the transfer switch are on 16” centers so they could line up on your studs if desired. We recommend using all four holes to mount the enclosure.

5.Select the bottom center 2” KO to exit to the Main distribution panel. Terminate the LOAD wires in the landing lugs on the bottom of the bus assembly, one to the Neutral lug and one to the Ground lug on the right side of the enclosure.

6.Terminate wires from the meter socket into the utility Main breaker on the left side, and the Neutral into the unused lug on the insulated neutral bar.

7.Plug in and wire any additional branch circuit breakers in the spaces provided. Installer will need to remove any hold-down strap to insert additional circuit breakers. Re-install hold-down strap after breakers are inserted.

8.Reinstall dead front cover and interlock mechanism if removed earlier. Fill any unused spaces in the dead front with the closing plates provided.

9.Reinstall cover.

2

Image 2
Contents Description Installation and Operating InstructionsTools and Items Needed for Installation Compatible Circuit Breaker TypesInstallation Procedure ModelTransferring from Generator Power to Utility Power Using Your Transfer SwitchTransferring from Utility Power to Generator Power Instructions dinstallation et dutilisation Outils et objets nécessaires pour linstallationModèle Étape 1 Procédure DinstallationDisjoncteurs compatibles Etape 2 Utilisation DU Commutateur DE Transfert Descripción Instalación e instrucciones de usoInterruptor DE Transferencia Manual Modelos 6335 y Herramientas y elementos necesarios para la instalaciónModelo Paso 1 Procedimiento DE InstalaciónTipos de disyuntores compatibles Paso 2 Usar SU Interruptor DE Transferencia