3 Installing the Switch
Stacking Switches
The switch supports stacking up to eight units through an optional SFP stacking transceiver. The stacking transceiver must be installed in the port 25 slot. Each stacking transceiver has two connectors, Tx and Rx, for attaching stacking cables. Figure
Note: The stacking transceiver must only be installed in the port 25 SFP slot.
Installing a Stacking Transceiver
The stacking transceiver must be installed in the port 25 slot. It should be inserted before any of the systems in the stack are powered on.
23 | 24 |
|
23
25
Tx
Rx
Remove Transceiver by Pulling Tab
Slide Transceiver into SFP Transceiver Slot
Figure 3-6. Installing a Stacking Transceiver
Slide the SFP transceiver into the SFP transceiver slot until it clicks into place. To remove, pull on the tab at the bottom of the front of the transceiver.