Before installation, re-installation, or troubleshooting
•Stop the application
•Switch off the power supply and pull out the mains plug.
•Relieve the application of any loads, which may be released during the work.
Before start-up
•Make sure that the system has been installed as instructed in the User Manual.
•Make sure that the voltage of the control box is correct before the system is connected to the mains.
•System connection. The individual parts must be connected before the control box is connected to the mains.
During operation
•Ensure that the cables are not damaged.
•Unplug the mains cable on mobile equipment before it is moved.
Information on the MJB
The MJB Modular Junction Box is designed for use together with OpenBus™ control boxes.
The MJB makes it possible to connect multiple handsets, attendant controls or it makes it possible to use the MJB as a control unit for 3rd party products as Out of Bed detection, USB charger, Under Bed Light etc.
LINAK A/S delivers only the OpenBus system and is not responsible for any products other than LINAK products (i.e. products from 3rd party suppliers) or the compliance of such products with the LINAK OpenBusTM system.