APC AP9628, AP9626 Connecting Equipment and Power to the Transformer, Rear Panels, Start-Up

Page 7

Connecting Equipment and Power to the Transformer

Connecting Equipment and Power to the Transformer

Rear Panels

AP9626 models:

AP9627 models:

AP9628 models:

Start-Up

Attention:

Wiring must be performed by a qualified electrician.

Adhere to all local and national electrical codes.

If the internal temperature of the transformer is less than 100ºF, one of the fans is at risk of failing. If 100ºF is reached, the redundant fan will turn on.

1.Check that all power is turned OFF.

2.For AP9626 (optional) or AP9628 models only, hardwire the transformer (see Hardwiring).

3.For AP9626 or AP9627 models only, connect all load equipment to the PDU receptacles.

Note: Each receptacle group is protected by a circuit breaker. A colored label identifies each circuit and the corresponding breaker.

4.Switch the transformer input circuit breaker ON.

5.Turn on output circuit breakers as needed.

6.Turn on all connected equipment.

APC Step-Down Transformer User Manual

7

Image 7
Contents APC Step-Down Transformer Page Introduction Environmental SpecificationsUnpacking Electrical Specifications Install the Rails Rack InstallationInstall the Transformer Hardwiring Electrical ConfigurationRear Panels Connecting Equipment and Power to the TransformerStart-Up Service Regulatory and Service InformationFCC Compliance Notice Regulatory Approvals American Power Conversion Limited Two Year Factory Warranty¹ Warranty and Contact InformationAPC Worldwide Customer Support