Sorting tasks

The “Plan > Sort tasks…” menu option may be used to sort the tasks in the task and gantt views by given task fields.

Baselines (saved work/start/end date)

Each task has a saved work/start/end date. This can be used to store a baseline for the task. A baseline records the calculated work/start/end date at a particular point of a project plans life. It is often useful to save a baseline when initially constructing a plan so that it can be compared at a later date when the plan is in progress.

The “Plan > Baseline…” menu option is used to copy the work/start/end dates into the baseline saved work/start/end date fields. This menu provides options for selecting which tasks the saved fields are updated. Just the currently selected task(s) may be updated, all new tasks (those where the saved fields are set to 0), any where the start date is in the future, all tasks in the plan.

Page 19 of 19

Image 19
Contents Plan for Nokia User Guide Introduction What is Plan?About this manual As a ZIP file for use with a Nokia 9210/9210i InstallationPre-installed on an MMC As a SIS filePurchase via post Purchase OptionsPurchase via the Internet Purchase via voice callPage Fundamental concepts Project PlanningCalculation of task dates ExampleCreating a new plan Fast Start TutorialCreating a new resource Creating tasks Setting dependenciesTransferring data between Plan and your desktop PC Summary tasksUpdating a task Sample PlanMPX file format KEY Features Page Task list view ViewsResource view Gantt viewHoliday view Editing tasks TasksCustom Fields Summary and sub-tasksCosts/Notes Baselines saved work/start/end date Sorting tasksResources Default work hoursUser notes. Freeform note associated with the resource Calculation/Storage Settings Calculation Settings and PreferencesPlan application Preferences