STEP 5 (See Diagram 5 & Cable Loop Diagram)
A.) | Attach the 118” Upper Cable (#59) to the opening on the front of the Upper |
| Frame (#4). Note: The Ball Stopper on the cable should be underneath the |
| Frame. |
B.) | Attach a Pulley (#62) to the opening. Secure it with one M10 x 2 ½” Allen Bolt |
| (#69), two Ø 7/8” x 5/8” Pulley Bushings (#44), and one M10 Aircraft Nut (#83). |
C.) | Draw the Cable over the Pulley towards the back of the machine to the second |
| opening on the Upper Frame. Repeat step B above to install a Pulley. |
D.) | Draw the Cable around the Pulley then pull back to the opening on the Front |
| Press Base (#6). |
E.) | Attach a Pulley to the opening on the Front Press Base. Secure the Pulley with |
| one M10 x 6 ¾” Allen Bolt (#97), two Ø ¾” Washers (#84), and one M10 Aircraft |
| Nut (#83). |
F.) | Draw the Cable around the Pulley and then to the opening on the Front Vertical |
| Frame (#3). Attach a Pulley to the opening. Secure it with one M10 x 2 3/8” Allen |
| Bolt (#70), two Ø 7/8” x ½” Pulley Bushings (#45), and one M10 Aircraft Nut |
| (#83). |
G.) | Draw the Cable around the Pulley then pull the Cable downwards. Attach the |
| Cable to two Double Floating Pulley Brackets (#23). Attach a Pulley and a L- |
| shaped Cable Retainer (#27) to the top holes on the Brackets. Secure them with |
| one M10 x 1 ¾” Allen Bolts (#71), two Ø ¾” Washers (#84), and one M10 Aircraft |
| Nut (#83). Let the Brackets hanging just for now. |
H.) | Pull the Cable upward to the opening on the rear of Upper Frame. Repeat B to |
| install a Pulley. |
I.) | Pull the Cable downward between the two Guide Rods to the Selector Rod (#14). |
| Thread the bolt at the end of the Cable into the opening on top of the Selector |
| Rod to secure the Cable. |
J.) | Connect a Chain (#66) to the Cable with a Hook (#67). Connect the Lat Bar to |
| the Chain with another Hook. Change the length of the Chain to the Cable to |
| obtain the desired Lat Bar exercises. |
15