C. Sidewalls/Surrounds

Adjacent combustible sidewalls must be located a minimum of 12 in. (305 mm) from the fireplace opening.

Combustible and noncombustible mantel legs, surrounds and stub walls may be constructed within the gridded area, Figure 6.3.

Grid represents 1 in. (25 mm) squares

12in.

[305 mm]

FLUSH

FRONT

50°

angle

 

36in.

[914 mm]

40in.

[1016 mm]

BRICK

FRONT

39°

angle

 

4in.

[102 mm]

9 3/4 in.

[248 mm]

12 in.

12 in.

[305 mm]

[305 mm]

Figure 6.3 Mantel Leg or Wall Projections (Acceptable on both sides of opening)

D. Frame the Fireplace

Figure 6.4 shows typical framing using combustible materials (2x4 lumber shown).

Observe all required air space clearances to combustible materials as shown in Figure 6.1 & 6.2.

Framing across the top of fireplace must be above top standoffs.

You must maintain

2 in. (51 mm) min. air space clearance from the chimney to the enclosure.

Note: Fireplace Header cannot be positioned until after the fireplace assembly is in place.

41 in.

(1041 mm)

23 in.

(584 mm)

Figure 6.4 Framing the Fireplace

20

Heat & Glo • HST-42D • 27177 • Rev AB • 11/08

Image 20
Contents Fire Risk Wood Burning FireplaceHot screen/mesh and glass doors will cause burns Number Listing Label Information/LocationGrate User Guide Table of ContentsInstaller Guide Warranty Hearth & Home Technologies Limited Warranty CONDITIONS, Exclusions & Limitation of LiabilityHeat & Glo HST-42D 27177 Rev AB 11/08 Listing and Code Approvals Appliance CertificationNon-Combustible Materials Combustible MaterialsHot glass will cause burns Operating InstructionsYour Fireplace Seasoned Wood Starting a FireGrate FirescreenGlass Doors Outside Air optionalVented Gas Log Sets & Gas Log Lighters Optional ComponentsWood Fuel Maintainance and Service Chimney Inspection/CleaningDisposal of Ashes Creosote Formation and Need for RemovalGlass Cleaning Check Firebox RefractoryInspect Grate Frequency As desiredTroubleshooting Guide Start Fire Problems Possible Cause SolutionGetting Started Typical Fireplace SystemNegative Pressure Design and Installation ConsiderationsDraft Locating Fireplace & Chimney Frequently open doors Central heat outlets or returnsInspect Fireplace and Components Tools and Supplies NeededFireplace System Requirements Framing & Clearances Select Fireplace LocationClearances Clearances to Combustible MaterialsSidewalls/Surrounds Frame the FireplaceInstallation of Fireplace Things to ConsiderPosition the Fireplace Place Protective Metal Hearth StripsFt min. from top of uppermost chimney section to air inlet Install Outside Air Kit AK14/AK18 InstallationChimney Assembly Chimney Requirements MetersUsing Offsets/Returns ExampleInstall Chimney Air Kit Assemble Chimney SectionsInstall Ceiling Firestops Installing the Ceiling FirestopInstall Attic Insulation Shield Prepare Attic Insulation ShieldComplete Installation Install FlashingFollowing steps should be skipped if using a chase Cut out Hole in RoofChimney Termination Requirements Flat RoofsChase Installations Construct the ChaseInstall Fireplace & Chimney Install Chase TopInstall Termination Cap ST375 Square Termination CapTS345/TS345P Square Termination Cap Shrouds Radiation ShieldField Constructed Shrouds Open Top Shroud TR342 caps require radiation shieldMailbox Style Shroud radiation shield required Roofed Style Shroud radiation shield required= 1/k x inches of thickness FinishingHearth Extension Finishing Material Noncombustible FacingCombustible Mantel Clearances to Mantels or other Combustibles above FireplaceSquares Accessories Gas Log/Lighter ProvisionWood Burning Inserts Gas Code, Ansi Z223.1Fireplace Dimensions Reference MaterialsChimney Components Catalog #14-1/2 10-7/8 276 mm Service Parts HST-42DDo not Discard this Manual