VENTING INSTALLATION INSTRUCTIONS

Installation for Vertical Termination

13

VENTING INSTALLATION INSTRUCTIONS

Continued

INSTALLATION FOR VERTICAL TERMINATION

Note: Vertical restrictor must be installed in all vertical installa- tions.

1.Determine the route your vertical venting will take. If ceiling joists, roof rafters or other framing will obstruct the venting system, consider an offset (see Figure 19) to avoid cutting load bearing members. Note: Pay special attention to these installation instructions for required clearances (air space) to combustibles when passing through ceilings, walls, roofs, enclosures, attic rafters, etc. Do not pack air spaces with insu- lation. Also note maximum vertical rise of the venting system and any maximum horizontal offset limitations.

2.Set the fireplace in desired location. Drop a plumb line down from the ceiling to the position of the fireplace exit flue. Mark the center point where the vent will penetrate the ceiling. Drill a small locating hole at this point.

Drop a plumb line from the inside of the roof to the locating hole in the ceiling. Mark the center point where the vent will penetrate the roof. Drill a small locating hole at this point.

Roof Flashing

Wall Strap

45° Elbow

Ceiling Firestop

Figure 19 - Offset with Wall Strap and 45° Elbows

Flat Ceiling Installation

1.Cut a 10 3/4" square hole in the ceiling using the locating hole as a center point. The opening should be framed to 10 3/4"x10 3/4" (273mm x 273mm) inside dimensions, as shown in Figure 9 on page 8 using framing lumber the same size as the ceiling joists. If the area above the ceiling is an insulated ceiling or a room, nail firestop from the top side. This prevents loose insulation from falling into the required clearance space. Otherwise, install firestop below the framed hole. The firestop should be installed with no less than three nails per side (see Figure 20).

2.Assemble the desired lengths of pipe and elbows necessary to reach from the fireplace flue up through the firestop. Be sure all pipe and elbow connections are fully twist-locked (see Figure 8, page 8).

3.Cut a hole in the roof using the locating hole as a center point. (Cover any exposed open vent pipes before cutting hole in roof.) The 10 3/4"x10 3/4" hole must be measured on the horizontal; actual length may be larger depending on the pitch of the roof. There must be a 1" clearance from the vent pipe to combustible materials. Frame the opening as shown in Figure 9, page 8.

4.Connect a section of pipe and extend up through the hole.

Note: If an offset is needed to avoid obstructions, you must support the vent pipe every 3 feet. Use wall straps for this purpose (see Figure 19). Whenever possible, use 45° elbows instead of 90° elbows. The 45° elbow offers less restriction to the flow of the flue gases and intake air.

5.Place the flashing over the pipe section(s) extending through the roof. Secure the base of the flashing to the roof and framing with roofing nails. Be sure roofing material overlaps the top edge of the flashing as shown in Figure 19. There must be a 1" clearance from the vent pipe to combustible materials.

6.Continue to add pipe sections until the height of the vent cap meets the minimum building code requirements described in Figure 7 on page 6. Note: You must increase vent height for steep roof pitches. Nearby trees, adjoining rooflines, steep pitched roofs and other similar factors may cause poor draft or down-drafting in high winds. Increasing the vent height may solve this problem.

7.Twist-lock the vent cap onto the last section of vent pipe.

Note: If the vent pipe passes through any occupied areas above the first floor, including storage spaces and closets, you must enclose pipe. You may frame and sheetrock the enclosure with standard construction material. Make sure and meet the minimum allow- able clearances to combustibles. Do not fill any of the required air spaces with insulation.

If area above is a room or

If area above is not a room, install

insulated area, install firestop

firestop below framed hole.

above framed hole.

 

Figure 20 - Installing Firestop

116236-01D

www.desatech.com

Image 13
Contents For Your Safety What to do if YOU Smell GAS For Your SafetySave this manual for future reference Safety Information Table of ContentsLocal Codes Product IdentificationPRE-INSTALLATION Preparation Product FeaturesLocation and Space Requirements 40 1/8 48 1/4 Horizontal Vent 26 1/2 Vertical Vent ClearancesTermination CAP AIR Supply Inlet GAS Meter Location of Termination CAPInstallation Precautions Venting Installation InstructionsHorizontal Termination Installation Installation PlanningInstalling Siding Standoff Combustible Vertical Horizontal H Horizontal Termination ConfigurationsCorner Installation Venting with Two 90 Elbows Horizontal System Installation Using TWO ElbowsFlat Ceiling Installation Installation for Vertical TerminationVenting with One 90 Elbow Vertical Termination ConfigurationsVertical Venting High Altitude InstallationFireplace Installation Venting InstallationInstalling Optional Blower Accessories Check GAS TypeBlower see Figure Model BKT InstallationBlower Wiring Diagram Installing GAS Piping to Fireplace LocationInstallation Items Needed Checking GAS Connections Connecting Fireplace to GAS SupplyOr servicing. Correct all leaks at once Pressure Testing Fireplace Gas Connections Installing Optional Wall Mount Switch GWMS2REMOVING/REPLACING Glass Door Installing Remote ReceiverRemoving Louver Panels Cleaning Glass Door Installing Lava Rock and Glowing EmbersRemoving Glass Doors For Your Safety Read Before Lighting Installing Brick Liner Models BL42DASA and BL42 DhasaOperating Fireplace Lighting InstructionsTo Turn OFF GAS Manual Lighting ProcedureTo Appliance Optional HAND-HELD Remote OperationManual Mode Safety FeaturesAuto Thermostatic Mode ON/OFF Series Model HRC100Pilot Assembly Operating Optional Blower AccessoryInspecting Burners Operating Optional GWMT1 Wall Mounted ThermostatGlass Door Cleaning and MaintenancePilot and Burners LogsObserved Problem Possible Cause Remedy TroubleshootingBrick Liner Models BL42DASA Above Gas leak. See Warning statementSpecifications Service Hints Replacement PartsTechnical Service Parts Under WarrantyIllustrated Parts Breakdown Models Parts ListCGCDV42NR, CGCDV42PR Series 19 18 Burner Assembly for Models Accessories Owners Registration Form Postage Required 116236-01D Keep this Warranty Warranty Information