Heat Controller SMA/SMH 18/24 installation instructions Gas Leak Check, Test Operation

Page 13
2. Gas Leak Check

Heat Controller, Inc.

INSTALLATION INSTRUCTIONS

SMA/SMH 18/24

 

 

 

2. Gas Leak Check

Make sure connections do not leak with leak detector or soapy water.

soapy water.

A. Lo packed valve B. Hi packed valve

C. End of indoor unit connection D. End of indoor unit connection

3. Test Operation

Test the unit’s operation after completing gas leak check at all flare nut connections and complete an electrical safety check.

A.

B.

C.

D.

E.

controlled by the remote controller to run in cooling mode. Manual operation must be used when the remote controller is disabled or when maintenance is necessary.

F. The test operation should last about 30 minutes.

12

Image 13
Contents INSTRUCTIONS INSTALLATIONSMA/SMH 18/24 Version C Single Zone Ductless Mini-SplitSystemPage INSTALLATION INSTRUCTIONS Installation PartsHeat Controller, Inc SMA/SMH 18/24INSTALLATION INSTRUCTIONS INDOOR UNIT INSTALLATION1. Attach the installation plate SMA/SMH 18/24INSTALLATION INSTRUCTIONS 2. Line Set and Condensate Drain LineHeat Controller, Inc SMA/SMH 18/24Page 5.Connecting Cables INSTALLATION INSTRUCTIONS 6. Piping and WrappingSMA/SMH 18/24 Heat Controller, Inc1. Outdoor Installation Precaution OUTDOOR UNIT INSTALLATION2. Drain Elbow Installation INSTALLATION INSTRUCTIONSINSTALLATION INSTRUCTIONS 3. Refrigerant Piping Connection2. Tightening Connection SMA/SMH 18/24INSTALLATION INSTRUCTIONS 4. Wiring ConnectionHeat Controller, Inc SMA/SMH 18/241. Air Purge AIR PURGE AND TEST OPERATION3. Test Operation 2. Gas Leak Check