1Installation of Outdoor Unit
Install according to Drawing for the installation of indoor and outdoor units
2Connection of pipes
●To bend a pipe, give the roundness as large as possible not to crush the pipe , and the bending radius should be 30 to 40 mm or longer.
●Connecting the pipe of gas side first makes working easier.
●The connection pipe is specialized for R410A.
Half union | Flare nut | Forced fastening without careful centering may | |
|
| damage the threads and cause a leakage of gas. | |
|
| Pipe Diameter(ǿ) | Fastening torque |
|
| Liquid side6.35mm(1/4") | 18N.m |
|
| Liquid/Gas side9.52mm(3/8") | 42 N.m |
|
| Gas side 12.7mm(1/2") | 55N.m |
Spanner | Torque wrench | Gas side 15.88mm(5/8") | 60 N.m |
Be careful that matters, such as wastes of sands, etc. shall not enter the pipe. The standard pipe length is 5m. If it is over 7m, the function of the unit will be
4 |
3 |
1(L) 2(N) |
Indoor unit
1(L) |
2(N) |
affected. If the pipe has to be lengthened, the refrigerant should be charged, according to 20 g/m. But the charge of refrigerant must be conducted by profes- sional air conditioner engineer. Before adding additional refrigerant, perform air purging from the refrigerant pipes and indoor unit using a vacuum pump,then
charge additional refrigerant.
CAUTION
Outdoor unit
Outdoor unit
B
Indoor unit
Power cable: ≥3G2.5mm2
Connecting wiring: ≥3G1.5mm 2 (For: L N )+2x0.75mm2
1. If the supply cord is damaged, it must be replaced by the manufacturer or its |
service agent or a similar qualified person. The type of connecting wire is |
2. If the fuse on PC board is broken please change it with the type of |
T. 3.15A/250V. |
Outdoor unit
Outdoor unit
A
B
A
Oil trap
Indoor unit
B
AIndoor unit
●Max.Elevation: Amax=15m
●In case the elevation A is more than 5m, oil trap shoud be installed every 5~7m
●Max. Length: Bmax=25m
●In case the pipe length B is more than 7m, the refrigerant should be charged, according to 20 g/m.
3. The wiring method should be in line with the local wiring standard. |
4. After installation, the power plug should be easily reached. |
5. A breaker should be incorporated into fixed wiring. The breaker should be |
than 3mm. |
3Connection
●Use the same method on indoor unit. Loosen the screws on terminal block and insert the plugs fully into terminal block, then tighten the screws.
●Insert the cable according to terminal number in the same manner as the indoor unit.
●If wiring is not correct, proper operation can not be carried out and controller may be damaged.
●Fix the cable with a clamp.
4Attaching Drain-Elbow
●If the
please attach it as figure. (Note: Only for heat pump unit.)
5Purging Method:To use vacuum pump
1.Detach the service port’s cap of
2.Open the handle at Iow in gaugemanifold, operate vacuum pump. If the scale- moves of gause (Iow) reach vacuum condition in a moment, check 1. again.
3.Vacuumize for over 15min.And check the level gauge which should read
handle ‘Lo’ in gaugemanifold and stop the operation of the vacuum pump. Check condition of the scale and hold it for
tightening, make flaring work again, the return to the beginning of 3 .
4.Open the valve rod for the
3