Friedrich SH15L30-A, SH20L50-A manual LOW Ambient Bypass Valve Figure, Equipment Must be Capable

Page 8

LOW AMBIENT BYPASS VALVE (Figure 9)

The HazardGard unit is designed to operate at low outside ambient temperatures. This is accomplished by the use of a bypass valve installed in the refrigeration circuit. The valve is connected between the discharge line at the compressor and the suction process tube. The valve responds to suction pressure which, when reduced in the system, causes the valve to open and bypass hot gas from the high pressure side to the low pressure side of the system. The hot gas entering the compressor mixes with the cool gas returned through the suction line, thus increasing the suction pressure. The valve is preset to open when the suction pressure reaches 50 psig. This pressure setting cannot be altered. The system can be operated at outdoor temperatures as low as 45° F before the evaporator coil will begin to accumulate frost.

To determine if the valve operates, block the return air to the evaporator coil. Turn on the unit and touch the tube at the bypass valve outlet which connects to the suction process tube. When the low side pressure reaches approximately 50 psig, the valve will begin to open and the tube will get hot. This method will determine if the valve is responding to the suction pressure change.

FIGURE 9

LOW AMBIENT Bypass

VALVE

SEALED REFRIGERATION SYSTEM REPAIRS

EQUIPMENT REQUIRED:

1.Voltmeter

2.Ammeter

3.Ohmmeter

4.E.P.A Approved Refrigerant Recovery System

5.Vacuum Pump (capable of 200 microns or less vacuum).

6.Acetylene Welder

7.Electronic Halogen Leak Detector (G.E. Type H-6 or equivalent).

8.Accurate refrigerant charge measuring device such as:

a.Balance Scales - 1/2 oz. accuracy

b.Charging Board - 1/2 oz. accuracy

9.High Pressure Gauge - (0-400 lbs.)

10.Low Pressure Gauge - (30" - 150 lbs.)

11.Vacuum Gauge - (0-1000 microns)

EQUIPMENT MUST BE CAPABLE OF:

1.Recovering CFC’s as low as 5%.

2.Evacuation from both the high side and low side of the system simultaneously.

3.Introducing refrigerant charge into the high side of the system.

4.Accurately weighing the refrigerant charge actually introduced into the system.

5.Facilities for flowing nitrogen through the refrigeration tubing during all brazing processes.

8

Image 8
Contents Service & Parts Manual Table of Contents Performance Data Cooling Component Operation and Testing Testing ProceduresCompressors Line Voltage OverloadFAN Motor Test Ground TestChecking Compressor Efficiency CAPACITOR, RUN Capacitor TestThermostat RangeTest Equipment Must be Capable LOW Ambient Bypass Valve FigureSealed Refrigeration System Repairs Equipment Required Hermetic Component Replacement Special Procedures in the Case of Compressor Motor BurnoutRotary Compressor Special Troubleshooting and Service Refrigerant ChargeTroubleshooting Problem Possible Cause To Correct Unit does not RUNTroubleshooting Problem Possible Cause To CorrectFAN Motor does Wiring Diagram Models SH15L30-A, SH20L30-A, SH20L50-AHazardgard Cabinet Parts Hazardgard Chassis Parts Hazardgard Parts List Description Part NO# Models Code Electrical PartsOptional Accessory Items Page Use Factory Certified Parts