Bryant 619CNQ, 619CNF START-UP Checklist Preliminary Information, Ii. Pre-Start-Up, III. Piping

Page 23

START-UP CHECKLIST

I. PRELIMINARY INFORMATION

 

OUTDOOR UNIT: MODEL NO. ___________________

SERIAL NO. ___________________________________

INDOOR UNIT: MODEL NO. _____________________

SERIAL NO. ___________________________________

ACCESSORIES: __________________________________________________________________________________

PISTONS: INDOOR SIZE: ____________

OUTDOOR SIZE: ____________

REFRIGERANT PIPING: EQUIVALENT LINE LENGTH: ____________

LIFT: FAN COIL ABOVE OUTDOOR UNIT? ____________

FAN COIL BELOW OUTDOOR UNIT? ____________

II. PRE-START-UP

INDOOR UNIT (REFER TO OUTDOOR UNIT INSTALLATION INSTRUCTIONS FOR OUTDOOR UNIT PRE-START-UP FUNCTIONS)

IS THERE ANY SHIPPING DAMAGE? ____________

IF YES, WHERE? ____________________________________

WILL THIS DAMAGE PREVENT UNIT START-UP? ____________

IS POWER SUPPLY CORRECT? ____________

HAS GROUND WIRE BEEN CONNECTED? ____________

HAS THE CORRECT SIZE FUSE OR HACR BREAKER BEEN PROVIDED? ____________

ARE POWER WIRES TO THE UNIT SIZED AND INSTALLED PROPERLY? ____________

IS THE DISCONNECT SWITCH INSTALLED WITHIN SIGHT OF THE UNIT? ____________

IS THE LOW-VOLTAGE CABLE (INDOOR TO OUTDOOR UNIT) RUN AND CONNECTED PROPERLY? ____________

HAS CONDENSATE DRAIN BEEN RUN, SLOPED AND TRAPPED PROPERLY? ____________

IS FILTER(S) IN PLACE? ____________

IS UNIT MOUNTED LEVEL? ____________

IS HEATING PISTON INSTALLED (FIG. 13), THE CORRECT SIZE, AND IN THE CORRECT DIRECTION? ____________

III. PIPING

IS A LIQUID LINE SOLENOID INSTALLED IF REQUIRED BY LONG-LINE APPLICATIONS? ____________

IS FILTER DRIER INSTALLED AT THE OUTDOOR UNIT? ____________

HAVE LEAK CHECKS BEEN MADE AT THE COMPRESSOR, OUTDOOR UNIT, FLARE CONNECTIONS, FILTER DRI- ERS, AND FUSIBLE PLUGS WITH A LEAK DETECTOR?* ____________

*FIELD PIPING AND ALL TUBING CONNECTIONS MUST BE LEAK TESTED BY THE PRESSURE METHOD DESCRIBED IN GENERAL TRAINING FOR AIR CONDITIONING MANUAL (GTAC2), MODULE 5. USE R-22 AT APPROXIMATELY 25 PSIG BACKED UP WITH AN INERT GAS TO REACH A TOTAL SYSTEM PRESSURE NOT TO EXCEED 245 PSIG.

HAS PIPING SYSTEM BEEN EVACUATED TO 1000 MICRONS (IF REQUIRED)? ____________

HAS SYSTEM CHARGE BEEN WEIGHED IN (IF REQUIRED)? ____________

HAVE SERVICE VALVES BEEN FULLY BACKSEATED? ____________

CHECK VOLTAGE: IS VOLTAGE WITHIN RANGE SHOWN FOR UNIT (WITH UNIT OPERATING)?

OUTDOOR ____________

INDOOR ____________

CL-1

Image 23
Contents Installation ContentsSafety Considerations Cooling System MatchesApplication Range System Type Indoor Section Number Outdoor Section NumberUnpack Unit Complete PRE-INSTALLATION ChecksBefore Installation Physical Data, Under Ceiling Cooling Only UnitsUnit Size Physical Data, Under Ceiling Heat Pump UnitsII. Select Location Ft-in Weight lbUnit SizeIII. Mount Unit IV. Connect Refrigerant Piping Installing Hex-Head Mounting Bolts Fan Coil UnitPiston and Charge Combinations Heat and Cool Systems Connect Condensate Drain LinePiston and Charge Combinations Cooling Only Systems Piston and Charge Combinations Heat Pump SystemsMounting Hanging Brackets AccuRater Metering Device at Service ValveElectrical Data VI. Make Electrical ConnectionsComponent Location Typical Ceiling-Suspended System Line Power Connections VII. Install ThermostatFPT ASMASR TranThermostats Heat Pump Systems VIII. Make Connections Between Indoor and Outdoor UnitsCheck AccuRater Metering Device Cooling Only SystemsCooling System Wiring Diagram Heat Pump Wiring Diagram START-UP III. Adjusting AirflowIV. Operating Mode Memory Automatic Operation AUTO. ModeII. AIR Filters FIG Cleaning and MaintenanceLubrication VI. Clean Condensate Drains III. Clean Indoor Unit Bottom PanelIV. Clean Indoor Coil Clean Outdoor Coil Outdoor UnitProblem Cause Typical Solution TroubleshootingCall for Free Catalog Service TrainingIII. Piping START-UP Checklist Preliminary InformationII. PRE-START-UP IV. START-UP START-UP Checklist