11-3. Grounding When Supplying Building Systems
| 1 | Equipment Grounding |
1 | 2 | Terminal |
GND/PE | 2 | Grounding Cable |
| Use #10 AWG or larger insulated | |
| copper wire. | |
| 3 | Ground Device |
. Use ground device as stated in electrical codes.
! |
23
! |
Ground generator to system earth ground if supplying power to a premises (home, shop, farm) wiring system.
Also see AWS Safety & Health Fact Sheet No. 29, Grounding of Portable And Vehicle Mounted Welding Generators.
11-4. How Much Power Does Equipment Require?
1 Resistive Load
3
2
1
3
VOLTS 115 AMPS 4.5
Hz 60
A light bulb is a resistive load and requires a constant amount of power.
2
Equipment with a motor is a
3 Rating Data
Rating shows volts and amperes, or watts required to run equipment.
Amperes x Volts = Watts
Example 1: If a drill uses 4.5 am- peres at 115 volts, calculate its run- ning power requirement in watts.
4.5 A x 115 V = 520 W
The load applied by the drill is 520 watts.
Example 2: If three 200 watt flood lamps are used with the drill from Ex- ample 1, add the individual loads to calculate total load.
(3 x 200W) + 520 W = 1120 W
The total load applied by the three flood lamps and drill is 1120 watts.