Grizzly G1028Z/G1029Z owner manual Test Run, To test run the machine

Page 18

10.Slip the bottom plastic collection bag over the bottom edge of the collector and tighten the clamp on the tightest notch possible.

Note: DO NOT force the clamp, choose the next notch over, then clamp in place.

11.Press the “Y” inlet onto the inlet cover flange, as shown in Figure 13. The inlet is secured to the collector body by a press-on fit.

Figure 13. Installing "Y" inlet.

-16-

Test Run

Do NOT put hands or small objects near inlet openings during opera- tion. Objects sucked into the inlet will hit the impel- ler blade. Failure to heed this warning could result in property damage or personal injury.

Once the assembly is complete, test run your machine to make sure it runs properly.

If, during the test run, you cannot easily locate the source of an unusual noise or vibration, stop using the machine immediately, then review the Troubleshooting on Page 29.

If you still cannot remedy a problem, contact our Tech Support at (570) 546-9663 for assistance.

To test run the machine:

1.Make sure you have read the safety instruc- tions at the beginning of the manual and that the machine is setup properly.

2.Make sure all tools and objects used during setup are cleared away from the machine..

3.Connect the machine to the power source.

4.Turn the machine ON.

5.Listen to and watch for abnormal noises or actions. The machine should run smoothly with little or no vibration or rubbing noises.

—Strange or unusual noises should be inves- tigated and corrected before operating the machine further. Always disconnect the machine from power when investigating or correcting potential problems.

6.Turn the machine OFF.

G1028Z/G1029Z Dust Collector

Image 18
Contents Dust Collector Page Table of Contents Introduction ForewordContact Info Machine Data Sheet G1028Z/G1029Z Dust Collector Machine Data Sheet G1028Z/G1029Z Dust Collector Safety Instructions for Machinery G1028Z/G1029Z Dust Collector Additional Safety for Dust Collectors Circuit Requirements G1028Z 110/220V OperationG1029Z 220V Operation 15 plug and receptacleItems Needed for Setup SetupSetup Safety Unpacking InventorySite Considerations Clean UpPlacement Location Floor LoadAssembly To assemble your machineUpper collection bag secured Test Run To test run the machineDesigning System General Duct MaterialMetal Duct Flexible Duct Plastic DuctSketch Your Shop Layout System DesignDecide Who Will Design Sketch a Basic Duct LayoutDetermine Required CFM of Each Machine MachineApproximate Determining Main Line Duct Size Determining Branch Line Duct SizeTotal CFM Branch Line Size Loss Per Foot Calculating Duct ResistanceDuct Approximate Dia Fitting 90˚ 45˚ Dia Elbow WyeYSystem Grounding Flex-hose grounded to machine Operation Safety OperationsGeneral Accessories Half-mask respirator with disposable Cartridge filtersMetal Branches Reducers & AdaptersMetal Elbows Schedule MaintenanceBag Cleaning LubricationService TroubleshootingDust Collector Operation G1028Z Wiring Diagram SwitchG1029Z Wiring Diagram G1028Z/G1029Z Parts Breakdown G1028Z Parts List G1029Z Parts ListPage Page Warranty and Returns