Grizzly G1028Z/G1029Z Calculating Duct Resistance, Duct Approximate Dia, Loss Per Foot

Page 24

Calculating Duct Resistance

Adding duct work, elbows, branches and any other components to a duct line increases airflow resistance (static pressure loss). This resistance can be minimized by using rigid (smooth) pipe and gradual curves, as opposed to flexible pipe and 90˚ elbows.

To help you think about this resistance, imagine riding a bicycle in a tunnel that is an exact replica of your duct work. If the inside of the tunnel is very bumpy (flexible pipe) and has a lot of sharp turns (90˚ elbows), it will take a lot more effort to travel from one end to the other.

The purpose of calculating the resistance is to determine if it is low enough from the machine to the dust collector to meet the given CFM require- ment for the machine. Use the charts in Figure 26 to calculate the resistance of duct work.

Duct

Approximate

Approximate

Dia.

Static Pressure

Static Pressure

 

Loss Per Foot of

Loss Per Foot

 

Rigid Pipe

of Flex Pipe

 

Main

Branch

Main

Branch

 

Lines

Lines

Lines

Lines

 

at 3500

at 4000

at 3500

at 4000

 

FPM

FPM

FPM

FPM

 

 

 

 

 

2"

.091

.122

.35

.453

 

 

 

 

 

2.5"

.08

.107

.306

.397

 

 

 

 

 

3"

.071

.094

.271

.352

 

 

 

 

 

4"

.057

.075

.215

.28

 

 

 

 

 

5"

.046

.059

.172

.225

 

 

 

 

 

6"

.037

.047

.136

.18

 

 

 

 

 

7"

.029

.036

.106

.141

8"

.023

.027

.08

.108

9"

.017

.019

.057

.079

 

 

 

 

 

Fitting

90˚

45˚

45˚

90˚

Dia.

Elbow

Elbow

Wye(Y)

Wye(Y)

 

 

 

 

 

3"

.47

.235

.282

.188

 

 

 

 

 

4"

.45

.225

.375

.225

 

 

 

 

 

5"

.531

.266

.354

.236

 

 

 

 

 

6"

.564

.282

.329

.235

 

 

 

 

 

7"

.468

.234

.324

.216

 

 

 

 

 

8"

.405

.203

.297

.189

 

 

 

 

 

Figure 26. Static pressure loss charts.

-22-

In most small/medium shops it is only necessary to calculate the line with the longest duct length or the most fittings (operating under the assumption that if the line with the highest resistance works, the others will be fine).

To calculate the static pressure of any given line in the system, follow these steps:

1.Make a list of each size duct in the line, includ- ing the length, and multiply those numbers by the static pressure value given in Figure 26.

2.List each type of elbow or branch and multiply the quantity (if more than one) by the static pressure loss given in Figure 26.

3.Add the additional factors from Figure 27 to your list.

Additional Factors

Static Pressure

 

 

Seasoned (well used)

1"

Dust Collection Filter

 

 

 

Entry Loss at Large

2"

Machine Hood

 

 

 

Figure 27. Additional factors affecting static

pressure.

4.Total your list as shown in the example in Figure 28 to come up with your overall static pressure loss number for that line.

Note: Always account for a seasoned filter, so you don't end up with a system that only works right when the filter is clean.

���������

��������������������������� ���������������� ����

�����������

��������������������������� ���������������� ����

������������������������ ������������������������ �����

���������������

��������������� �������������������������������� ����

������������ ���������������������������������������� ����

������������������

��������������� �������������������������������� �����

��������������������� ������������������������ �����

Figure 28. Totaling static pressure numbers.

G1028Z/G1029Z Dust Collector

Image 24
Contents Dust Collector Page Table of Contents Introduction ForewordContact Info Machine Data Sheet G1028Z/G1029Z Dust Collector Machine Data Sheet G1028Z/G1029Z Dust Collector Safety Instructions for Machinery G1028Z/G1029Z Dust Collector Additional Safety for Dust Collectors Circuit Requirements G1028Z 110/220V OperationG1029Z 220V Operation 15 plug and receptacleSetup Setup Safety UnpackingItems Needed for Setup InventoryClean Up Placement LocationSite Considerations Floor LoadAssembly To assemble your machineUpper collection bag secured Test Run To test run the machineDesigning System General Duct MaterialMetal Duct Flexible Duct Plastic Duct System Design Decide Who Will Design Sketch Your Shop Layout Sketch a Basic Duct LayoutDetermine Required CFM of Each Machine MachineApproximate Determining Main Line Duct Size Determining Branch Line Duct SizeTotal CFM Branch Line Size Calculating Duct Resistance Duct Approximate DiaLoss Per Foot Fitting 90˚ 45˚ Dia Elbow WyeYSystem Grounding Flex-hose grounded to machine Operation Safety OperationsGeneral Accessories Half-mask respirator with disposable Cartridge filtersMetal Branches Reducers & AdaptersMetal Elbows Maintenance Bag CleaningSchedule LubricationService TroubleshootingDust Collector Operation G1028Z Wiring Diagram SwitchG1029Z Wiring Diagram G1028Z/G1029Z Parts Breakdown G1028Z Parts List G1029Z Parts ListPage Page Warranty and Returns