REMOVING MACHINE FROM SHIPPING SKID
B
C
Fig. 6
A
Fig. 5
1. Open door (A) Fig. 5, under infeed table and remove mounting hardware that fastens infeed end of machine to skid
2.Remove three screws (B) Fig. 6, and remove cover (C) from dust chute located under outfeed table. Remove mounting hardware located inside cover (C) that fastens outfeed end of machine to skid and replace cover (C).
3.Remove machine
from shipping skid and position in permanent location.
THE
JOINTER IS VERY
HEAVY AND A
FORKLIFT OR HOIST
WITH STRAPS UNDER
THE TABLE
BRACKETS SHOULD
BE USED TO MOVE
THE MACHINE.
Figure 7 illustrates the machine removed from the shipping skid.
Fig. 7
SELECTING FLOOR SPACE
It is important that the machine be set on a solid, level foundation. If rocking occurs, place metal shims at the corners between the base and the floor. Lag screws or bolts may be used if desired to secure the machine to the floor using the same holes that fastened the machine to the shipping skid.