ASSEMBLY & INSTALLATION (CONT.)
Frame Lock, Sash Lock, and Foam Seal Installation
MOUNTING HARDWARE
6
3/4” Screws
Sash Lock | 1 |
2. To secure the lower sash into place, use the sash lock and a 3/4” screw as shown below (See FIG. 11)
FIG.11
Tools Needed:
Phillips Screw Driver
Drill (if plot holes are needed)
1.Drive 3/4” screws into the top of the accordion panel frame and the top rail to securely attach the window air conditioner to the lower sash. (See FIG. 9/10)
FIG.9
FIG. 10
3. For added insulation, cut the supplied insulation foam to the width of the window. Insert the foam between the window sashes to prevent air and objects from getting into the room. (See FIG. 12)
FIG. 12
Removing the Air Conditioner from the Window
1.Turn the air conditioner off, and disconnect the power cord.
2.Remove the sash seal from between windows, and unscrew sash lock.
3.Remove the screws installed through the frame and frame lock.
4.Close (slide) the side panels into frame.
5.Keeping a firm grip on air conditioner, raise the sash and carefully “rock” air conditioner backward to drain any condensate water in base of unit. Be careful not to spill any remaining water while lifting unit from window.
6.Store parts WITH the air conditioner in the box