ELECTRICAL INSTALLATION
1.Enter electric enclosure with properly sized feeder leads. Be sure to properly ground the water heater.
2.Install these power leads into the box lugs on the terminal block or magnetic contactor.
3.Torque screws per torque chart included in Section VI.
4.All other electrical connections are made at the factory; therefore, no other electrical connections are necessary.
FINAL CHECKS
1.Check all connections for tightness.
2.Ensure that all the above steps are completed
3.After the water is heated for the first time, monitor the water temperature as described in Section III, Quarterly Inspection.
13