ELECTRICAL INSTALLATION

1.Enter electric enclosure with properly sized feeder leads. Be sure to properly ground the water heater.

2.Install these power leads into the box lugs on the terminal block or magnetic contactor.

3.Torque screws per torque chart included in Section VI.

4.All other electrical connections are made at the factory; therefore, no other electrical connections are necessary.

FINAL CHECKS

1.Check all connections for tightness.

2.Ensure that all the above steps are completed

3.After the water is heated for the first time, monitor the water temperature as described in Section III, Quarterly Inspection.

13

Image 13
Contents Electric Heater Company BOX Hubbell Electric Heater CompanySTRATFORD, CT Table of Contents Section Title Page Tank Section I General Description and ConstructionTank Connections Heating ElementControl Thermostat Temperature High Limit SwitchOuter Shell and Insulation Magnetic ContactorOptions Low Water Cut-OffFused Low Voltage Transformer Dial Temperature and Pressure GaugeVacuum Relief Valve Electro-Mechanical Timer On/Off SwitchIndividually Fused Elements Built-in Circuit BreakerSecuring of Heater Water Heater PlacementMounting Dimensions Filling the Heater Piping InstallationFinal Checks Electrical InstallationMaintenance and Operation Section III Scheduled Maintenance and OperationFreezing Quarterly InspectionAnnual Inspection Symptom Probable Cause Corrective Action / Remedy Section IV TroubleshootingPage Surface Temperature High Limit CUT-OFF Section V Servicing & Replacement of PartsImmersion Temperature High Limit CUT-OFF Heating Element Page Surface Mounted Thermostat Immersion Thermostat Magnetic Contactor Relief Valve Formulas Section VI Miscellaneous Charts and Formulas Element ChartTorque Values Section VII ABS Type Approval Program Page Page