Honeywell PRO-2200 Specification, Primary power 12VDC±10% 400mA Relay contacts, Inputs

Page 15
Specification

PRO-2200 Two Reader Module PRO22R2

Installation Guide

15

5.Connect wiring to alarm input sensors or install jumper wire as appropriate.

6.Connect relay output wiring as appropriate.

7.Connect communications wiring to the Intelligent Controller.

8.Recheck wiring for correct connections and continuity.

9.When all boards have been installed, connect the Power Supply Cord for proper connections and power.

10.Setup the panel controls using the host software.

Specification

The Two Reader is for use in low voltage, class 2 circuits only.

Primary power: 12VDC±10% 400mA

Relay contacts:

Relays 1 & 3 outputs, Form-C, 5A @ 28 VDC, resistive

Relays 2 & 4 & 5 & 6 outputs, Form-C, 2A @ 28 VDC, resistive

Inputs:

8 supervised, End of Line resistors 1k ohm ± 1% tolerance 2 unsupervised dedicated inputs

Reader interface

 

 

Reader power

 

5 VDC (5 - 6.2) or 12 VDC (pass-through) 150mA max. each

Reader LED output

TTL compatible, high > 3V, low < 0.5V, 5mA

 

 

source/sink max.

Reader buzzer output

Open collector, 5 VDC open circuit max. 10mA sink max.

Reader data inputs

TTL compatible inputs

Communication:

 

 

RS-485

9,600 to 38,400 bps

Wire requirements:

 

 

Power

1 twisted pair, 18AWG

RS-485:

24AWG, 4,000 feet (1,200m) max., 2-twisted pair with shield (120,

 

23pf) (Belden 9842 or equivalent.)

Alarm inputs

1 twisted pair per input, 30 ohms max.

Outputs

As required for the load

Readers

6 conductors, 18AWG, 500 feet (150m) max. shield and drain

Mechanical:

 

 

Dimension

5.5" (140mm) W x 9" (229mm) L x 1" (25mm) H

Weight

12 oz. (340g) nominal

Environment:

 

 

Temperature

0°C to +49°C, operating, –55°C to +85°C, storage

Humidity

0% to 85% RHNC

Image 15
Contents PRO-2200 Two Reader Module Installation Manual Part Number PRO22R2A division of Northern Computers, Inc Page Contents Fire Safety and Liability Notice Warnings and CautionsPage Unpacking Procedure DisclaimerProduct Liability Mutual Indemnification Limited Warranty Shipping InstructionsTo ship equipment back to Engineered Systems Confidentiality Installation GuidePRO-2200Two Reader Module PRO22R2 Default Set UpDescription SettingPRO-2200Two Reader Module PRO22R2 Dipswitch Settings= Default Installation GuideMODE PowerLED Operation CommunicationsReader Wiring For Wiring to an RS-485portFor wiring to a reader port LED Output Alarm Contact WiringControl Output Wiring Single Wire Reader LED Control ConfigurationSuggested Installation Sequence Mounting OptionsSee diagram to follow Reader interface SpecificationPrimary power 12VDC±10% 400mA Relay contacts InputsSeparate - Power VDC Supply + Wiring Diagram for Connectors 1 throughInstallation Guide Power VDCWiring Diagram for Connectors 6 through Installation GuidePRO-2200Two Reader Module PRO22R2 PRO-2200Two Reader Module PRO22R2 Installation GuidePage 2700 Blankenbaker Pkwy, Suite Louisville, KY Honeywell Security & Data Collection