GENERAL INFORMATION

LOCATION AND CLEARANCE

Make sure your installation location provides adequate combustion and ventilation air.

In selecting the location, the aesthetic and functional uses of the appliance are primary concerns. However, vent system routing to the exterior and access to the fuel supply are also important. Consideration should be given to traffic ways, furniture, draperies, etc., due to elevated surface temperatures. The location should also be free of electrical, plumbing or other heating/air con- ditioning ducts. Be sure to maintain adequate clearances around air openings into combustion chamber.

The appliance should be mounted on a fully supported base extending the full width and depth of the unit. The appliance may be located on or near conventional construction materials. However, if installed on combustible materials, such as carpeting, vinyl tile, etc., a metal or wood barrier covering the entire bottom surface must be used.

Right and left sides of the unit are determined when standing in front of the unit.

Minimum clearance to combustibles: sides and back - 0", floor - 0" , adjacent wall to Front - 6".

Minimum clearance to combustibles for the vent system is 2" when passing through a wall or chase.

ASSEMBLY STEPS—OVERVIEW

The typical sequence of installation follows. However, each installation is unique resulting in variations to those described.

1.Construct framing and position the appliance.

2.Route gas supply line and bring in electrical service line to appliance location.

3.Install vent system.

4.Make connection to gas supply and electrical service.

5.Install the log assembly.

6.Install the remote thermostat (optional).

7.Test fire the burner.

8.Install glass panel.

9.Finish enclosure walls and trim.

5

Image 7
Contents Approved for Mobile Home Installation Page Table of Contents Page MIN. Input IntroductionPage Location and Clearance Assembly STEPS-OVERVIEWInstallation Interior Horizontal General Information Exterior Vent Locations and Restrictions MIN Horizontal Termination Vent AssemblyHorizontal Termination Connecting Vent Cap with Horizontal Vent Pipe Vertical Termination Vertical Termination Installation High Altitude Natural GAS Propane LPGGAS Pressure Checks GAS Valve ConnectionOperating Instructions OperationControl Knob Page Page Pilot and Flame Glass Door InstallationPage Accessories or Options General Maintenance MaintenanceServicing Replacement PartsKEY# Part Description Part Number Replacement Parts Part Description Part Number Additional Replacement PartsConditions and Exclusions WarrantyWarranty ProcedureOther Rights