7.Slide the wall firestop over the vent pipe before connecting horizontal run to vent cap (see Figure 12).

8.Carefully move fireplace, with vent assembly attached, toward wall and insert vent pipe into horizontal termination. The pipe overlap should be a minimum of 11/4".

9.Slide wall firestop against interior wall surface and attach with screws provided. See Figure 13 for horizontal termination details.

10.Place fireplace into position and shim with noncombustible material if needed. Nail or screw side flanges to framing to secure unit in place. IMPORTANT: Make sure fireplace is level before securing. If fireplace is not level it will not work properly.

Cut Siding Away to Fit Standoff

Standoff

Wood Screw

Vent Cap

Minimum Pipe

Overlap 11/4"

Direct Vent

Pipe

Wall

Firestop

Maintain 1"

Minimum Air

Space Around

Outer Pipe When

Penetrating a Wall

10" x 10" Framed Opening

Siding Standoff

Screws

High Wind

Termination

Apply Mastic to

Outside Edge of

Standoff

Exterior Wall with Vinyl Siding

Screws

Apply Mastic to

All Four Sides

Figure 11 - Installing Siding Standoff

Interior Wall

Surface

Wall

Firestop

Vent Cap

Horizontal

(Horizontal

Vent Pipe

Termination)

 

Screw

Figure 12 - Connecting Vent Cap with Horizontal Vent Pipe

Figure 13 - Typical Horizontal Termination Cap Mounting with

Additional Siding Standoff Installed

108860-01D

www.desatech.com

Image 9
Contents What to do if YOU Smell GAS For Your SafetySafety Information Table of ContentsProduct Features Product IdentificationLocal Codes Pre-Installation Preparation Location and space requirementsClearances Framing and finishing Framing Clearances for Installation Against an Exterior Wall Termination CAP AIR Supply Inlet GAS Meter Location of Termination CapInstallation Precautions Venting Installation InstructionsInstallation Planning Horizontal Termination InstallationVent Pipe Connections Installing Siding Standoff Square Termination Horizontal Termination ConfigurationsVenting with Two 90 Elbows Snorkel Termination InstallationOffset with Wall Strap and 45 Elbows Flat Ceiling InstallationVertical Venting Vertical Termination ConfigurationsHigh Altitude Installation Fireplace InstallationParts lists for venting kits and components Installing optional blower accessoriesBlower Model BK Model BKT InstallationInstalling Gas Piping to Fireplace Location Blower Wiring DiagramInstallation Items Needed Installation Items Needed Connecting Fireplace to GAS SupplyPressure Testing Fireplace Gas Connections Pressure Testing Gas Supply Piping SystemChecking GAS Connections Test Pressures In Excess Of 1/2 Psig 3.5 kPaUnplug fireplace. Let cool before installing brick liner Cleaning Glass DoorRemoving/Replacing Glass Door Removing Louver PanelsInstalling Log No Installing logs, lava rock and glowing embersInstalling Logs No and No Wiring Diagram Wall Switch InstallationOptional Remote control Installation model WRC Operating Fireplace For your safety read Before lightingLighting Instructions To Turn OFF GAS To AppliancePilot assembly Operating optional Blower accessoryInspecting Burners Burner Flame PatternGlass Door Cleaning MaintenancePilot and burners LogsTo clean pilot. This can damage pilot unit TroubleshootingTop above Gas leak. See Warning statement atService Hints Replacement PartsTechnical Service SpecificationsAccessories Illustrated Parts Breakdown VT32EPRB Parts List109 Parts List 23-5 23-3 23-4 23-2 23-1 VT36ENR 109 2917 KEY Description Keep this Warrant Warranty Information