Weil-McLain LGB-23 manual Junction box assembly dual base boilers, III Wiring - continued

Page 8
3.Attach control transformer(s) to junction box(es).

LGB-6 to LGB-23Series 2 – Control Supplement

III Wiring – continued

Wiring Procedure 1. Determine right or left electrical supply wiring.

2.Attach electrical junction box(es) to inside jacket end panel. Screws and nuts are provided. For dual base boilers, use offset nipples (provided) to connect junction boxes together, then hang junction boxes by screwing top box to boiler jacket. See Figure 4, below.

3.Attach control transformer(s) to junction box(es).

4.Drill 1/8" hole in interior jacket panel midway between ignition control panel and left jacket panel. Mount wire support clip using sheet metal screw (furnished).

5.Complete wiring per wiring diagram, Figure 3 (pages 6 and 7).

“Hot” side of line voltage to boiler must be wired directly to limit circuit, then fed to transformer primary(ies). Dual Base: “R” terminal of secondaries are to supply power to bases independently of each other. Do not wire “R” terminals together.

6.Install pilot proving and main flame proving ground connections as shown in Figures 1 and 2 (page 3) and Figure 3 (pages 6 and 7). Route wires through wire support clip.

7.Canada only - attach chain between junction box(es) and transformer with S-hooks.

Figure 4

Junction box assembly dual base boilers

Screw Holes

Junction Box

to Mount

Base 1

Junction Box

 

to Jacket

 

Offset Nipples

(2)

Junction Box

Base 2

911BGLr0

8

Part Number 550-141-916/1001

Image 8
Contents Part Number 550-141-916/1001 Part Number 550-141-916/1001 Part Number 550-141-916/1001 Natural gas supply pipe sizing II Gas pipingLGB-6to LGB-23 Series 2 - Control Supplement III Wiring Universal Control System - Natural gasIII Wiring - continued SCHEMATIC WIRING DIAGRAMPRE-WIREDPANEL NO. 1 BASE WIRINGWiring diagram LADDER WIRING DIAGRAMUniversal Control System - Natural gas Natural GasJunction box assembly dual base boilers III Wiring - continuedLGB-6to LGB-23 Series 2 - Control Supplement 3.Attach control transformers to junction boxesPart Number 550-141-916/1001 IV Operating instructionsUniversal Control System - Natural gas V Verification testing Manual test firing valveLGB-6to LGB-23 Series 2 - Control Supplement Verify boiler control sequenceVI Parts list - continued Parts drawingUniversal Control System - Natural gas Part Number 550-141-916/1001Part Number 550-141-916/1001 LGB-6to LGB-23 Series 2 - Control SupplementWeil-McLain 500 Blaine Street Michigan City, IN